1.0 PRE-COMMENCEMENT REPORT

1.1 Demolition

  • Demolition completed?

  • If No, Client to advise of Demolition date

1.2 Rubbish/Debris

  • Rubbish/debris to be removed?

  • If Yes, Client to advise of removal date.

1.3 Grass/vegetation

  • Grass/vegetation to be cut prior to starting work?

  • If Yes, Client to advise of removal date.

1.4 Trees

  • Trees on site to be removed prior to starting work?

  • If Yes, Client to advise of removal date.

1.5 Footpath

  • Damage to footpath? (take pic either way)

  • If Yes, Client to note.

1.6 Kerb & Gutter

  • Damage to kerb & gutter? (take pic either way)

  • If Yes, Client to note.

1.7 Boundary Fence

  • Is there damage to boundary fence? (take pic either way)

  • If Yes, Client to note.

1.8 Fill

  • Excess fill to be removed following excavation? (please note approx loads)

  • Fill required? (please note approx loads & check contract for PA)

  • If Yes, Extra costs may be incurred. Client to be present on date of removal/importation to monitor.

1.9 Rock Shelf

  • Can rock shelf be seen?(if Yes, take photograph)

  • If Yes, excess costs may be incurred for rock breaking and removal

1.10 Power lines

  • Power lines-tiger tail insulation required?(if Yes to service main or service to house? If unsure notify WHS Manager for safety assessment)

  • If Yes, excess costs may be incurred.

1.11 Cranes

  • Extra cranes required?

  • Would normal deliveries be affected due to site conditions?

  • If Yes, excess costs may be incurred for double handling and crane hire.

1.12 Traffic Control

  • Is traffic control required(if Yes check contract for PA)

  • If Yes, excess costs may be incurred.

1.13 Site Location-Coastal

  • Is site within 1km of the ocean or non surf coast?(if yes check contract and selections)

  • If Yes, excess costs may be incurred.

1.14 Retaining Walls

  • Is a retaining wall required after site is excavated? (if Yes Fowler to assess and immediately advise client)

  • Note: Excavations over 1m in depth will not start unless there is prior consultation with Fowler Homes Pty Ltd

Supervisor Sign off

  • I supervisor of above mentioned site certify items raised in this report are true and correct as of date below

  • Signature

2.0 Internal use only

  • Is site classified as tight site?(if Yes what trades will be affected?)

  • Sewer affected? (supervisor to check plans, if Yes ensure all plans are correct)

  • Are all pegs in place?

  • Is Tree protection zone Required?

  • All weather access on site ordered?

  • Is existing boundary fencing 1.8m high?

  • Fencing ordered?

  • Sketch boundary where temporary fence is required

  • Water on site?

  • Have you organized Safety Signage, Padlock and WHS Management Plan for site? (advise WHS Manager)

  • Is site in close proximity to school or park?(if Yes notify WHS Manager)

  • Is traffic management plan required?

  • Will scaffold require shade cloth?(if Yes notify scaffolder)

  • Would normal deliveries be affected due to site conditions? internal note: if Yes, supervisor to contact transport company prior to frame delivery)

COMMENTS

  • Comments/recommendations

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.