Title Page
-
Pre-Concrete ITP
-
Site Address
-
Concrete location. (e.g. Garage slab, Level 2 slab etc..)
-
Conducted on
-
Prepared by
-
Pour Description
- Slab on Ground
- Suspended slab
- Footing
- Block-Fill
- Formwork
- AFS / Dincel
Concrete supply & specifications
-
Concrete on site time booked
-
Concrete supplier
-
Concrete mix ordered
-
Quantity/ Volume ordered - M3
-
Any additive or accelerator?
-
Test required?
-
Has concrete supplier been advised how trucks should enter the site?
-
Are traffic management services required?
-
Pump washout area confirmed to pump operator?
Personnel
-
Formwork Contractor
-
Steelworker
-
Pump Contractor
-
Concrete Finishing Contractor
-
Engineer
-
Certifier
-
Electrician
-
Plumber
Pre-Concrete Placement
-
Have all dimension been checked against the architectural and engineer's drawings and RFI's that pertain to this area?
-
Are all Hobs/Upstands/downturns formed per the drawings?
-
Check set-downs for wet areas (min 50mm)
Suspended Slab
-
Ensure formwork deck for suspended slabs are set to the right height
-
Ensure formwork A-frames have cross bracers both sides
-
Check rebates sizes and positions under sliding doors
-
Have all minimum clear cover requirements been achieved?
-
Has all reo and mesh been checked against Engineer drawings?
-
Has the Engineer attended site to inspect and sign off?
-
Has the engineer requested/authorised photos in lieu of site visit?
-
Has the Certifier attended site to inspect and sign off?
-
Has termite protection been installed?
-
Have adequate supports (chairs) been installed so that reo and wire mesh remain in position during the pour?
-
Is the vapour barrier installed correctly
-
Have dowels been checked for proper placement?
-
Are starter-bars at correct centers and alignment?
-
Stormwater, drainage and hydraulic pipework installed, retained and checked?
-
Plumber's ITP Received?
-
Are all electrical conduits and fitments installed and Electrician's ITP Received?
-
Are Floor wastes all set and at the proper RL for falls?
-
Are there any sleeves, recesses or misc items that need to be placed?
-
Has expansion material been placed at all the specified locations.
-
Is formwork clean and free of debris/rust/scaling ?
-
Pictures - Include all areas and at least 10 photos
-
Acceptance Signatures:
-
Signature- Site Manager
-
Signature Engineer
-
Signature - Certifier
-
Signature Formworker
-
Signature