Information
-
Site conducted
-
Works Type
- Drainage
- Right of Way
- Footpath Works
-
Site Address
-
Location
-
Conducted on
-
Council Representative
-
Contractor/s (include contact details)
-
Other Personnel Present (include company & position)
-
Engineering Approval Letter & Plans sited
General
-
Proposed construction works Commencement Date (relating to drainage or right of way works)
-
Proposed construction works Completion Date (relating to drainage or right of way works)
-
Defects Liability /Maintenance Period
-
Bond/Guarantee Amount
-
Bond received
Plans & Approvals
-
Traffic Management Plan
-
VicRoads MoA
-
Council Arborist Approved Works
-
Dilapidation Report
-
Engineering Approval Conditions “prior to works<br>commencing”
-
Technical Permits Issued
- Works Consent
- Road Occupancy Permit
- Drainage Inspection Permit
- Vehicle Crossing Approval
- Asset Protection Permit
- Work Zone Permit
-
Technical Permits Outstanding
- Works Consent
- Road Occupancy Permit
- Drainage Inspection Permit
- Vehicle Crossing Approval
- Asset Protection Permit
- Work Zone Permit
-
Notification Letter sent to residents
Hold Points & Witness Points
-
Drainage Works
- Prior to the backfilling of stormwater drains
- Prior to backfilling subsoil drains
- Prior to connection of house and property connections to stormwater drains
- Prior to covers being placed on pits
- Prior to construction of table drains
-
Other Civil Works
- Prior to pouring concrete on large reinforced concrete structures and footings
- At proof rolling of subgrade
- Prior to the placement of each pavement course
- Prior to placement of kerb and channel
- Prior to pouring of footpaths and driveways
- Prior to the placement of the primer coat
- Prior to the placement of first asphalt course or sealing
- Prior to placement of each fill layer
- Prior to construction of retaining walls
-
Landscaping Works
- Prior to removal of native vegetation and other existing vegetation
- Prior to planting (landscaping)
-
Other Inspections
- Works Completion Inspection
- Final Inspection - Release From Maintenance Period (and bond)
Existing Conditions
-
Note existing infrastructure, include photos of footpaths, nature strips, fences, etc.
Consent to proceed to construction
-
Council Representative
-
Contractor Representative