Title Page
-
Conducted on
-
Prepared by
-
Location
-
Which network?
-
G17 number?
-
NRO number?
-
Installation Company Name
-
Installer's Name
-
Install start date
-
Type of audit
Installation
-
Type of Installation
-
What type of installation is it?
AUDIT FINDINGS
-
Is there a copy of the G17 Project file on site?
-
Is the G17 (Parts A-F) included in the project pack?
-
Is Part C of the G17 signed by the User(s)?
-
Is there an approved NRP available on site?
-
Is the Competent Person named on the NRP on site and controlling the works?
-
Are the end-to-end test sheets available?
-
Have adequate electrical isolations been carried out by an EL/6 authorised person?
-
Has the installation been completed as per the approved G17 design?
-
Have all electrical tests and inspections including hazardous area initial inspections been completed and the results fully documented?
-
Have all installation and commissioning works been completed by approved competent personnel?
-
Is there a full set of project 'As Built' project drawings available on site?
-
Are there any other existing drawings that have not been updated that should have been modified?
-
Have all affected drawings been reviewed and marked up where necessary?
-
Has a full copy of the 'As Built' project drawings and any other affected drawings been sent to the Statutory Records team?
-
Has a full copy of the 'marked up' drawings been left on site?
-
Has the newly installed E&I asset data been collected using the approved ADC template?
-
Has the site been left tidy?
-
Have all relevant documents been signed off (i.e. G17 Parts D & E and the relevant sections in the NRP?
-
Any other comments?