Title Page
-
Site conducted
-
Machine(s) serial number
-
Conducted on
-
Prepared by
Pre-operation checklist
-
Check all welds around the baler for damage
-
Check visible hydraulic connections and pipes for leaks or damage
-
Check all panel bolts are tight and panels are in place
-
Check for any oil leakage around the bailer
-
Check feeder is clear
-
Check power lead for any damage
After start-up
-
Check all the safety sensors / interlocks are working as they should
-
Run the baler to ensure the ram moves freely within the machine
Cleaning
-
(Make sure the power is isolated before cleaning commences, please initial if OK, or mark with an X if
unsafe) -
Clean all debris from the lifting arm and inside cage.
-
Remove debris from around the baler:
-
Open panels at back and clean out card debris behind the ram if applicable:
-
Jet wash the baler and around it. (as per site schedule)
At end of shift
-
Isolate baler and padlock in place
-
If any faults are found report to helpdesk and put machine out of order
-
I can confirm all checks have been completed
-
List any issues identified during the operation and action taken
-
Operator Name and Signature