Information
-
Location
-
Asset No.
-
Client
-
Shift:
-
Date:
Pre Start Checklist
-
A Pre Start Checklist must be completed at the beginning of every shift or before operating other machinery during the shift. These are intended as a minimum standard and should not override specific Plant requirements and the client's site requirements.
1.0 CATEGORY (A) MINOR DEFECTS
-
Drill Rigs with MINOR defects may operate. Defects are to be reported as an action item, communicated to the Supervisor / Maintenance staff immediately.
-
Walk Around Inspection – Leaks, Hazards, Damage
-
Mud Pump, Water Pump, Pressure Washer – Oil, Fuel leaks
-
General Housekeeping
-
CDS Asset #, Control Panel Labels and Warning Labels/Stickers (Present & legible)
-
Access/Egress (Ladders, self-closing gates and walkways)
-
Cooler Pack Clean
-
All Gauges Working
-
All Grease Points Greased
2.0 CATEGORY (B) MODERATE FAULTS
-
Drill Rigs with MODERATE defects may only operate with approval from the Shift Supervisor.
Defects are reported as an action item to Supervisor/Fitter immediately, AND the Supervisor/Fitter has been consulted for approval and this pre start sign off has been completed by the authorising person. -
Hydraulic Hoses – Wear, Leaks, Connections
-
Water Hoses & Whip Checks/Shackles – Wear, Leaks, Connections, Valves
-
Check Oil Levels – Engine, Hydraulics, Bean Pump, Rotation Head and Funk Box (If applicable)
-
Other Fluid Levels - Fuel, Coolant, AdBlue
-
Start Up/Warning Alarms
-
Condition of Break Out (Inserts and greased)
-
Condition of Subs/Haul Plug (Threads, greased and inspections current)
-
Condition of Foot Clamps (Inserts and greased)
-
Condition of Rod Spinner (Inserts, alignment and greased)
-
Condition of Overshot Assembly & Safety Chain (Splice, inspection current, lifting dogs)
-
Condition of Track Base (Frame, Rollers, Plates)
-
Remote Condition/Operation (All functions work and free from damage)
-
Batteries – Water Level, Cables Conditions
-
Mast Lights Operational
3.0 CATEGORY (C) MAJOR DEFECTS
-
Drill Rigs with MAJOR defects may only operate with approval from Maintenance Manager or Core Drilling Management.
Defects are reported as an action item to Management / Maintenance Manager immediately, AND Management / Maintenance Manager has been consulted for approval and this pre start sign off has been completed by the authorising person. -
Check For Any Tags – Isolation Switch (Ensure they're clearly labelled and operational)
-
Check Fire Extinguishers and Fire Suppression are tagged and in date
-
Inspect Fan, Guards, Belts – Ensure Good Condition
-
Check Pressure Relief Valve (PRV) is in date
-
What is the next expiry date of the PRV/S
-
Rotation Cage/Proximity Switches working correctly
-
How did you test the function of this proxy?
-
Deadman Switch/Overrides are Operational (Breakout/Rod Spinner slew. If applicable)
-
Winch/Wireline Limiters Operational?
-
Check condition of Winch Rope /Wireline (Wear, Condition & Certification)
-
Mast Pivot Points/ Stay Rods
-
Check E-Stops (Push to engage, twist to reset), ensure they're clearly identifiable and labelled
-
Check manual actuators – ensure safety pins and anti-tamper ties are in place and that all secure, clean, undamaged and accessible
COMMENTS
-
Rig Hours
-
Please state any additional relevant information from the Inspection
COMPLETION
-
Operator Name & Signature
-
Authorising Supervisor (Signature)
-
Comments