Job activities
-
Job activities
- Set columns
- Set beams
- Set plank
- Set walls
- Grout
- Weld
- Detail
Pre task checklist
-
New employees on site orientated
-
First aid kit available and stocked
-
Live utilities clearly marked
-
Proper safety equipment on site
-
Proper tools for the job
-
Review SDS of hazardous substance that might be used
-
Communicated work with others working in the are
-
Rescue plan in place
-
Proper signage in place
-
Area barricaded or taped off
-
Caps on all rebar
-
Job scope understood
-
Fire extinguisher in proper location
-
Check rigging
-
Load chart
-
Check oil in welder
-
Fuel before use
-
Leads check
-
Ear plugs, gloves, safety shoes, safety glasses
-
Monitor
-
Crane size
Identify potential hazzards
-
Lower equipment with rope
-
Particle in eye/ cutting, grinding, wind
-
Over exertion/ back and shoulders
-
Rigging for lifts
-
Live utilities above and below ground
-
Possible electric shock
-
Fall protection over six feet
-
Traffic moving equipment
-
Fire/ welding sparks
-
Cutting torch
-
Heat/ cold exposure
-
Slips/trips/falls
-
Confined space
-
Lead/asbestos
-
Loud noises/ tools/ equipment
Identify hazard elimination
-
Face shields/ goggles
-
Proper positioning, get help lifting when needed
-
Clear area for overhead lifts/ good hand signals
-
Inspect rigging equipment
-
Erect barricades to protect from above and below
-
Gopher on call, all lines clearly marked
-
All GFCI's in place and working
-
Proper PPE
-
Pinch points
-
Fall protection/ guard rails/ 6' CAZ line
-
Plenty of fluids/ dress in layers
-
Good housekeeping
-
Don't do it, get the experts
List additional hazards
-
Additional hazards
Near misses
-
Near miss
How near miss may have been avoided
Crew members
-
Add signature
-
Add signature
-
Add signature
-
Add signature
-
Add signature
-
Add signature
-
Add signature
-
Add signature
-
Add signature