Titelseite

  • Ort der Durchführung

  • Durchgeführt am

  • Vorbereitet von

  • Standort
  • Personnel Present

Inspektion

Site Acceptance

  • The site has been accepted at handover

  • After the recruitment has started, there was no delay resulting in negative financial losses for the business (e.g Penalties vs HR Costs and possible outbookings by changing opening dates).

  • If additional costs were caused, by whom were they covered? Construction, NSO, Hotel P&L or external

  • Recruitment - Is there adequate TM, TLs, Technician & Management for the start of the site operations

  • Are all delivered orders (by NSO) in the hotel

External structures

  • All external signage is in place and illuminated (where applicable)

  • The exterior is free of litter and presentable

  • All external structures (e.g. external bin room, terrace, outside guest entrance) are safe, locked and pose no risk of fire

  • External structures media upload

Reception & Office

  • The digital screen displays the correct information

  • The office is set up in a clean and tidy way according to HSS and finance requirements, with keys stored securely and lockable HR cabinets

  • All system related items are working - PMS, Micros, PEDs, EBD & key cutting system, printer, emails and E2N

  • Reception and office media upload

Public Area

  • The hardware and communication devices are all working correctly including Wi-Fi and telephone lines

  • All public areas are clean and to German brand standards with all fixtures and fittings in place according to furniture and fire plan

  • The atmosphere of the public area is up to PI standards (i.e. music, scent and lighting scenes)

  • All the relevant signage is in place and the wayfinding is appropriate

  • The public toilets all have their relevant fittings and are ready for guests to use (UA toilets to HSS standard)

  • The lifts are clean, working, have clear relevant signage and access control

  • Public Area media upload

Kitchen, Bar & Buffet

  • The buffet is set up to standard and all equipment is in working order (i.e. coffee machine, cold well, hot tap, juice dispenser). There is enough space for chilled <br>food/drinks, for hot food and for all other food/drinks or an acceptable alternative is available

  • The bar is fully equipped and ready for operation (i.e. beer tab, ice machine, glassware)

  • A full stock count has been completed, a test order has been placed and stock go live has been successfully completed

  • All the hand washing facilities are fit for purpose,equipped with the defined PI products including drying and relevant signage according to HSS Standard

  • The kitchen is set up according to hygienic standards and all equipment is in place & functioning (i.e. Rational is included in the online connected cooking platform)

  • Kitchen, Bar & Buffet media upload

Back of House & Team facilities

  • The back of house areas are clear of construction materials, clean and well maintained

  • The team room is finalised to standard, clean and comfortable with all equipment provided working

  • The team smoking area is far away from linen and is in a clear, well ventilated location and not directly outside guest bedrooms

  • The team changing facilities are clean and adequate for operation

  • BOH & Team room media upload

Linen Rooms & Storages

  • All the linen rooms are organised neat, tidy and clearly labelled

  • There is an archive room, a maintenance store, empty bottle storage zone and these are adequate for site operations

  • The linen strategy enables the team to clearly divide clean and dirty linen, e.g two rooms or seperated in a room (e.g. dry wall)

  • Linen Rooms media upload

Plant Rooms & Roof

  • All relevant health and safety signage is displayed as appropriate in the plant rooms

  • The plant rooms are secure and clear of everything other than<br>permanent fixtures

  • The roof is clean, secure and clear of anything other than permanent<br>fixtures and the relevant safety measures are in place (i.e. PPE available)

  • Plant Room and Roof media upload

Rooms - Construction

  • How many rooms (of those who have been handed over by opening) have been desnagged and are fit for sale

  • Quality and quantity issues from suppliers (i.e. headboards) are noted and are being followed up (With Dates)

  • Is the close out tracker up to date with all open issues including responsibility, time line and solution e.g. construction defects, warranty etc.

  • The technical equipment and installations in the guest rooms are functioning (i.e. A/C, hot and cold water, lighting, etc.)

  • All UA rooms have had the relevant fixtures & fittings installed, the emergency alarm has been tested and has been responded to.

  • Rooms Media Upload

Car Park

  • The car park is clean, well lit and free of all construction material/ storage

  • The car park has functioning hardware, the team has been trained on how to use the software and it is sufficient for the hotel operation

  • Car Park media upload

Health Safety & Security

  • All licences have been applied for - Gewerbeanmeldung, Gaststättenerlaubnis (if applicable), GEMA, GEZ, DEHOGA

  • A fire evacuation drill according to Brandschutzordnung Teil B has been trained and performed

  • Water quality test has been completed, has passed and the documentation is handed to Operations

  • The acceptance of the lifts has taken place

  • There are sufficient smoke detectors

  • There are no protective caps on the smoke detectors

  • The fire alarm system is fully functional

  • The installed video cameras cover all important areas of the hotel and the positioning complies with the PI standard

  • The video cameras are in operation

  • Access to the building for the fire brigade is guaranteed at all times

  • With what percentage did the HSS (NSO) audit pass

  • With what percentage did the HSS (Construction) audit pass

  • Health Safety & Security media upload

Facility management

  • All mandatory maintenance contracts are in place and a FM strategy has been agreed with the hotel - E.g. Lifts, BMZ, Electrical

  • The team knows where the emergency gas & water shut off valves are and have received all relevant mechanical and electrical training

  • The house technician knows how to use Ostara and has the necessary access

  • The team has received a defined set of spare parts and know where to order replacements (i.e. paint, flooring, tools)

  • Is the temperature in lobby and guest areas set up according to standard

  • The Hotel Manager knows the defect reporting procedure and who to contact in emergencies

  • Facility Management media upload

Operational Compliance/Procedures - Operations

  • The Hotel Manager is trained on Fusion process and confirms understanding/where to go to for support

  • The Hotel Manager can confirm that all team members have the<br>correct right to work documentation and uploaded to Personio

  • All sections in the hotel manager skills log have been signed off and completed

  • The Hotel Manager is trained on the finance policy, has signed the FPPM and completed KCSA training

  • The Hotel Manager has read the brand standards and confirms to follow these accordingly

  • The Hotel Manager can confirm that they understand the weekly/monthly stock management processes including counting and<br>entering stock figures and where to store the appropriate documentation?

  • The Hotel Manager is trained in Groups and AC Procedures, confirms understanding and where to go to for suppport

  • The Hotel Manager confirms understanding of his business partners within the Support Centre and cluster

  • The Hotel Manager confirms receipt, understanding and implementation of "Sicherheitshandbuch"

  • With what percentage did the Sign Off list Team Member pass

  • With what percentage did the Sign Off list Team Leader pass

Sign Off

  • New Openings Project Manager

  • Property Manager

  • Skills Trainer

  • Hotel Manager

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.