Information
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Time of arrival
-
Time of departure
Panel Checks
-
Is the system Monitored
-
Type of Signalling equipment
-
The following checks on the intruder/hold-up alarm installation have been completed in accordance with BS 9263 2016.
-
Installation meets the ‘as fitted’ document
-
Tamper detection<br>NOTE Check at least one tamper for correct operation through to the CIE.<br>
-
Setting and unsetting<br>NOTE Offer user(s) refresher system operation training, if required.<br>
-
Entry and exit procedures
-
Power supplies, including any APS.<br>(Testing of batteries and current readings)<br>
-
Quiescent Current _________________mA
-
Alarm Current _________________mA
-
Battery Calculations to verify suitability. Q x 11.5 + A x 0.5 = _________ x 1.25 = _________ C Min
-
Battery Fitted ________ah - Suitable YES/NO
-
What size Battery is installed ?
-
Functioning of detectors and HD’s<br>(Full Walk test of system, Test PA buttons in normal Day Mode)<br>
-
Environmental conditions for adverse effects<br>(Check all detection is not damaged by water ingress or blocked)<br>
-
What Adverse effects are present
-
Operation of warning devices<br>(including removal of the hold off voltage to the external sounder, this should operate the unit until the hold off supply is restored)<br>
-
Operation any ATS <br>(NOTE all paths must be tested)<br>
-
What could not be tested and why ?
-
Visual inspection for potential problems <br>(electrical and physical)<br>
-
What Is the problem ?
-
Care should be taken to ensure the equipment is properly reinstated after testing.
-
Engineer Comments
-
Additional Work Required
-
What additional work is required ?
Parts required for repair
-
Are replacement parts required
-
What parts are required to repair fault
-
Have replacement Parts been installed
-
What Parts have been used
Customer Acceptance
-
Customer name :
-
Customer Signature
Job completion
-
I hereby certify that the works described above have been carried out and have been completed to my satisfaction. I agree that any outstanding works have been explained and I agree to arrange for any outstanding or further works described under the "Further action required by client" section above to be carried out. I also undertake to ensure payment of any applicable charges. Current standard charges plus any parts costs.