Information
-
Product Audit - Trenching & Pipe Laying
-
Document No.
-
Observer
- NJB
- CIT
- GAO
- SHM
- BJP
- LCD
- BSR
-
Conducted on
Chainage
-
General information:
-
Chainage to: Chainage from:
-
Easting
-
Northing
Safety
-
Is there a JSEA on-site?
-
Is safety signage been displayed?
-
Is minimum on-site safety standards been maintained e.g. (PPE, flashing beacon, reverse parking)
-
Is the required trench depth greater than 1500mm?
-
Has the trench been battered or benched to the safety standard of maximum 1500mm depth?
Pre-start requirements
-
If required, has the contractor had a pre-start FPP briefing be an FPO?
-
Has the pipeline construction corridor been marked on ground and maintained?
-
Have all Machinery Exclusion (NO GO) Zones been flagged and maintained.
-
Add media
Landowner Access Agreement
-
Have property / land tenure boundaries been identified and marked?
Trenching & Pipe Laying Activity
-
Is the pipeline clearing corridor width a maximum of 25m and within the projects design corridor?
-
Has the trench been dug to the correct depth for the pipe size?
-
Has bedding and haunching material been screened to a max size of 25mm?
-
Is haunching material being compacted properly?
-
Is the trench width within the standards for the size of pipe?
-
Is 150mm cover of screened material being achieved?
-
Has the marker tape been installed using the correct method and at the right depth?
-
Is a minimum total cover of 750mm above the pipe being achieved?
Fire Prevention
-
If required, is there fire fighting equipment on-site as per an approved FPP?
-
Add media
-
If required, is the contractor doing daily fire weather observation and recording?
-
Add media
-
General observations:
Notes
Sketches
-
Add drawing
Photos
-
Add media
Sign Off
-
Add signature