Title Page
-
Building
-
Area
-
Elevation
-
Works
-
Commencement Date
-
Certa Manager
Installation
Type of Works
-
Type of Works
- E&I Rainscreen Cladding
- E&I bridge single ply
- E&I bridge link decking
- E&I composite roof
- Terrace roof
- Key worker block single ply
Breather membrane
-
Have correct materials been delivered to site?
-
Has breather Membrane been installed in line with Certa Construction issue drawings?
-
Has Membrane been inspected by a Certa Manager?
-
Can the next stage of Installation be carried out?
-
Evidence
Galv Supports
-
Have correct materials been delivered to site?
-
Have Galv supports been installed in line with Certa Construction issue drawings?
-
Have Supports been inspected by a Certa Manager?
-
Can the next stage of Installation be carried out?
-
Evidence
Fire Barrier
-
Have correct materials been delivered to site?
-
Have brackets been fixed 250mm max from ends?
-
Have brackets been fixed 500mm max cts?
-
Has fire barrier been installed in line with latest fire strategy and Certa construction issue drawing?
-
Has fire barrier been inspected by a Certa manager?
-
HOLD POINT RELEASE
-
Can the next stage of installation be carried out?
-
Evidence
Insulation
-
Have correct materials been delivered to site?
-
Has Insulation been installed in line with Certa Construction issue drawings?
-
Has insulation been inspected by a Certa Manager?
-
Can the next stage of Installation be carried out?
-
Evidence
Mullion and Helping Hand Brackets
-
Have correct materials been delivered to site?
-
Have mullions and Helping hand brackets been installed in line with Certa Construction issue Drawings?
-
Have Mullions and Brackets been inspected by a Certa Manager?
-
Can the next stage of Installation be carried out?
-
Evidence
Rainscreen
-
Have Correct Materials been deliver to site?
-
Have Hook on Rainscreen panels been installed in line with Certa construction issue drawings?
-
Has Rainscreen been inspected by a Certa Manager?
-
Can Snagging Inspection be carried out?
-
Evidence
Gutters
-
Has correct material been delivered to site?
-
Have gutters been installed in line with Certa construction issue drawings?
-
Have gutters been checked by a Certa manager?
-
Can next stage of installation be carried out?
-
Evidence
Firth Galvanised Deck
-
Has correct material been delivered to site?
-
Has Galv deck been installed in line with Certa construction issue drawings?
-
Had deck been inspected by a Certa manager?
-
Can next stage of installation be carried out?
Spectravap VCL
-
Has correct material been delivered to site?
-
Has VCL been installed correctly with 150mm minimum lap
-
Has spectravap jointing tape been installed correctly and consistently?
-
Has VCL and tape been inspected by a Certa manager?
-
Can the next stage of installation be carried out?
-
Evidence
Insulation
-
Has correct material been delivered to site?
-
Has Enertherm gold insulation been installed correctly with staggered joints?
-
Has insulation been fixed 9no fixings per board (15no on perimeter)
-
Has insulation been checked by a Certa manager?
-
Can the next stage of installation be carried out?
-
Evidence?
IKO Armourplan
-
Has correct materials been delivered to site?
-
Have peel tests been carried out daily?
-
Has IKO Armourplan been installed correctly with 140mm minimum lap (110 min on end lap)?
-
Have gutters been installed and checked?
-
Have walkways and extras been installed and checked?
-
Has Armourplan been checked by a Certa manager?
-
Can final QA checks be carried out?
-
Evidence
Firth Deck
-
Have correct materials been delivered to site?
-
Have gutters been installed correctly?
-
Has deck been installed in line with Certa construction issue drawings?
-
Has butyl tape been installed as per detail?
-
Has deck been Fixed at correct centres?
-
Has deck been stitched at correct centres?
-
Has deck been checked by a Certa manager
-
Is area ready for final QA checks?
-
Evidence?
Composite roof
-
Has correct material been delivered to site?
-
Have gutters been installed correctly?
-
Have composite panels been installed in line with Certa construction issue drawings?
-
Has butyl tape been installed correctly?
-
Has panel been fixed at correct centres?
-
Has panel been stitched at correct centres?
-
Has panel been checked by a Certa manager?
-
Can final QA checks be carried out?
-
Evidence
Primer
-
Has correct material been delivered to site?
-
Has primer been installed in line with IKO installation guidelines?
-
Has primer been checked by a Certa manager?
-
Can next stage of installation be carried out?
-
Evidence
VCL
-
Have correct materials been delivered to site?
-
Has VCL been installed in line with Certa construction issue drawings?
-
Has VCL been checked by a Certa manager?
-
Can next stage of installation be carried out?
-
Evidence?
Insulation
-
Have correct materials been delivered to site?
-
Has insulation been installed in line with Certa construction issue drawings?
-
Has insulation been checked by a Certa manager?
-
Can next stage of installation be carried out?
-
Evidence
Single Ply
-
Have correct materials been delivered to site?
-
Has single ply been installed in line with Certa construction issue drawings and IKO installation guidelines?
-
Has Single ply been checked by a Certa manager?
-
Have any walkways or extras been checked by a certa manager?
-
Can final QA checks been carried out?
-
Evidence
Composite panels
-
Has correct material been delivered to site?
-
Have gutters been installed correctly?
-
Have composite panels been installed in line with Certa construction issue drawings?
-
Has butyl tape been installed correctly?
-
Has panel been fixed at correct centres?
-
Has panel been stitched at correct centres?
-
Have all ridge flashings, sealents and foam fillers been installed correctly?
-
Has panel been checked by a Certa manager?
-
Can final QA checks be carried out?
-
Evidence
Spectravap vapour control layer
-
Have correct materials been delivered to site?
-
Has VCL been installed in line with IKO installation guidelines?
-
Has VCL been checked by a Certa manager
-
Can the next stage of installation be carried out?
-
Evidence
Enertherm Gold 140mm insulation
-
Have correct materials been delivered to site?
-
Has insulation been installed in line with IKO installation guidelines?
-
Has insulation been checked by a Certa manager?
-
Can the next stage of installation be carried out?
-
Evidence
IKO Armourplan (mechanically fixed)
-
Have the correct material been delivered to site?
-
Has Singleply been installed in line with IKO installation guidelines?
-
Has singleply been checked by a Certa Manager?
-
Can the next stage of installation be carried out?
-
Evidence
Walkways and Extras
-
Have walkways and any extra's been installed in line with Certa construction issue drawings and manufacturer guidelines?
-
Have walkways and extra's been checked by a Certa manager?
-
Can final QA checks be carried out?
-
Evidence
Parapet and capping
-
Has correct material been delivered to site?
-
Have parapets and capping been installed in line with Certa construction issue drawings?
-
Have parapet and capping been checked by a Certa manager?
-
Evidence
Snagging
Snagging
-
Have any Snags been identified?
-
Photo
-
Have Snags been Rectified?
-
Photo
Senior Manager QA Checks and Handover
Certa QA Manager Final (or Senior Certa Manager) Inspection
-
Have all items on QA form been filled in?
-
Have any 3rd party test or inspection reports been carried out?
-
Is area snag free and ready for handover?
-
Have final QA checks been carried out?
-
Is area ready for handover?
Handover
-
On behalf of Certa Roofing and Cladding LTD
-
Signature
-
On behalf of Galliford Try
-
Signature