Title Page

  • Site

  • Location of Inspection

  • Prepared by

  • Conducted on

  • Personnel

Requirements

  • Are the latest revision of Jessella Details and Elevation drawings on site and being followed?

  • Are the latest revisions of Rockwool Installation Manuals on site and being followed?

  • Has the Installation Method been read and understood by all operatives?

Rockwool SP120 Vertical Cavity Barrier

  • Have the Cavity Barriers been cut to the correct cavity depth?

  • Have the Cavity Barriers been installed using the correct brackets and fixings?

  • Have the Cavity Barriers been installed fully, uninterrupted by the Horizontal Barriers?

  • Are the Cavity Barriers installed tightly abutted to each other?

  • Are their at least 2 fixings per Cavity Barrier?

  • Does the Cavity Barrier stand proud of the Vertical Rail by at least 45mm?

Rockwool OSCB44 Horizontal Fire Barrier

  • Have the Cavity Barriers been cut to the correct cavity depth?

  • Does the Cavity Barrier sit 25mm behind the Vertical Rail?

  • Have the Cavity Barriers been installed using the correct brackets and fixings?

  • Do the Cavity Barriers abut tightly to each other and to the Vertical Barriers?

  • Are their at least 2 fixings per Cavity Barrier?

  • Have Rockwool Pigtails been installed to the face of the Cavity Barrier and protrude out at least 25mm?

Rockwool 100mm Duoslab

  • Have the Insulation Slabs been installed using the correct fixings?

  • Have the Insulation Slabs been installed in a 'brick' style?

  • Have the Insulation Slabs been installed tightly abutted to each other and Cavity Barriers?

Aluminium Framing

  • Have the Aluminium C-Channels been installed using the correct fixings and following setting out drawings?

  • Have the Helping Hand Brackets been installed using the correct fixings and following setting out drawings?

  • Have the Aluminium Vertical Rails been installed using the correct fixings and following the setting out drawings?

  • Have the Aluminium Rails been installed plumb?

  • Have the Aluminium Rails been installed to allow for deflection?

  • Have the Aluminium 'Z' Carrier Rails been installed using the correct fixings and following the setting out drawings?

  • Has a section of OSCB Intumescent Strip been installed to the front of the Carrier Rail at Vertical Fire Barrier Locations?

Matrix SF Aluminium Cassettes

  • Has the Framing, Insulation and Cavity Barriers been inspected and signed off?

  • Have Anti-Rattle Clips been installed?

  • Has the gap in between the top hat sections to the rear of the panel been filled with intumescent silicone?

  • Have the Cassette Panels been fully engaged into the Carrier Rails?

  • Have the Cassette Panels been secured at the top with the correct fixings?

Site alterations

  • Are there any site alterations?

Drawings

  • Relevant drawings

Comments

  • Are there any comments?

Sign off

  • The below signatures deem all Jessella works mentioned In this report complete to drawings and handed over to Barratt London.

  • Checked on behalf of Jessella

  • Checked on behalf of Client

End of inspection

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.