This Site Safety Inspection forms part of the Fortec Weekly Inspection requirements for Post Tensioning works to requires all works to comply with statutory and regulatory authorities.
Supervisor Assessment
-
Are the Daily Pre-starts and Daily Site Diary entries up to date. Are weekly Tool Box Talks being conducted?
-
Are all employees aware of the Emergency Procedures and know where fire equipment is placed?
-
Are Employees aware of the location where First Aid facilities are placed?
HOUSEKEEPING
-
Are walkways and work areas clear and free of trip hazards?
-
Are safety signs in place and located in the appropriate positions?
FALL PROTECTION
-
Is there perimeter protection/handrails in place?
-
Are all penetrations covered or isolated?
PPE
-
Are long shirts, long pants, gloves, glasses and other required PPE being worn correctly and is in good condition?
PLANT & EQUIPMENT
-
Is plant & equipment maintained and used correctly and records maintained? (Pre-starts, maintenance records etc)
-
Is electrical equipment tested and tagged?
-
Are "Out of Service" tags available for use on site?
-
Are electrical leads suspended?
-
Is guarding in place and adequate to prevent injury? (i.e. can a body part penetrate through the guarding and cause injury?)
-
Are ONLY 7" approved Fein grinders in use? Have all operators of Grinder equipment completed their VOC? Is double eye protection worn by the operator?
ENVIRONMENT
-
Are hazardous substances used and stored according to their SDS?
-
Is there adequate placement of bins and is rubbish being disposed of correctly?
-
Confirm that there have been no hazardous spills on site?
QUALITY ITEM AND PROCESSES
-
Are PCF's being completed for each stage of the works and submitted to the client?
-
Is ALL equipment calibrated and certificates current?
-
Are Strand Test certificates visible on open coils? The technician is to ensure that a coil in use has the test certificate attached to the Bripac at ALL times.
-
Note any improvements you consider necessary. Use this space for additional comments.
Sign off
-
SUPERVISOR