Title Page

  • Site conducted

  • Project

  • Client

  • Subcontractor

  • Conducted on

  • Lead Auditor

  • Audit Team

  • Document No.

  • Location
  • Executive Summary

1 - Status of previous Audit

  • 1.1 Actions from the previous audits and current status? (Closed, Outstanding)

2 - General

  • 2.1 Are project documents being kept in an effective manner? (Folder structure complete and easy to find)

  • 2.2 HSQE Resources? (Access to GiMS, BIM360 and K.Now and training provided)

  • 2.3 Site Daily Log? (Maintenance)

  • 2.4 Supplier process been undertaken? (Approved vendor)

3 - Health & Safety

  • 3.1 Latest H&S report?

  • 3.2 Method Statement and Lifting Plan? (Reviewed and submitted)

  • 3.3 Have managers inspections been carried out? (H&S)

  • 3.4 Are accident / incident being reported? (Via email)

  • 3.5 PUK and Subcontractor carrying out H&S meetings? (Daily / Weekly)

  • 3.6 GiMS Hazard Alert. (Once a Week)

  • 3.7 High Risk Review of activities? (Method Statement Review Register being recorded once a Month)

4 - Quality

  • 4.1 Site Inspection Test Plan (ITP)? (Approved Status A)

  • 4.2 BIM 360 checklist. (Recorded as per the ITP)

  • 4.3 Client acceptance pre-handover protection of work areas? (Checklists)

  • 4.4 Calibration certificates available? (PUK and Subcontractor)

  • 4.5 Evidence of PUK sampling Subcontractor works? (As per ITP %)

  • 4.6 GiMS Nonconformance Management? (Treatment approval / Operative closure and Economical closure)

  • 4.7 Benchmark report? (Approved and status)

  • 4.8 Structural Silicone Glazing? (Training and records available)

5 - Environment

  • 5.1 Waste being managed on site? (Segregated and properly disposed of)

  • 5.2 Closedloop scheme compliant on site? (Correx and polythene)

  • 5.3 Project Aspect & Impact Register? (Issued, controlled and cascaded to operatives)

  • 5.4 Emergency Preparedness Procedure? (Cascaded to operatives)

  • 5.5 Waste Management Procedure? (Cascaded to operatives)

6 - Continual Improvement

  • 6.1 Comments

7 - Close out Meeting

  • 7.1 Close out meeting undertaken?

  • 7.2 PUK Manager(s) available.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.