Title Page
-
Site conducted
- 21 Moorfields
- Battersea 3B
- 8 Bishopsgate
- 20 Ropemaker
- KGX1 Google
- IQL S4
- Nova N2
-
Conducted on
-
Prepared by
-
Location
Untitled Page
0. Status of previous Audits.
-
undefined
1. Documents
-
Initial Phase of the Project
-
1.1 Has the Kick Of Meeting taken place?
-
1.2 Has the PIMP been prepared and sent for comments?
-
1.3 Have the ITP been prepared by PUK, accepted by the client?
-
1.4 Installation Methodology / Presentation available (Has the plan been developed and broadcast to interested parties)?
-
1.5 Approved Mock up Reports/Samples
-
1.6 Is there an approved up to date installation programme?
-
1.7 Calibration register populated and up to date?
-
1.8 RAMS, Lifting Plan and Temporary Works register populated and up to date?
-
1.9 Are installation drawings available to Subcontractor?
-
1.10 Subcontractor selection process been undertaken e.g. PQQ?
-
1.11 Is Benchmark being installed in accordance with approved status?
2. Checklist
-
2.1 Are checklist created as per the ITP (sampled from ITP)?
-
2.2 Is reference drawing available?
-
2.3 Do the checklists identify measuring equipment and the serial number? (certificates available and current)
-
2.4 Can PUK demonstrate that they are inspection subcontractor works as per ITP (percentage)?
-
2.5 Checklist status?
-
2.6 Checklist register?
3. Area Handover
-
3.1 Are pre-protected working areas being accepted by the client? (Checklists)
-
3.2 Area Handover Status?
-
3.3 Area Handover Register?
4. NCR
-
4.1 Have the NCRs been raised on BIM 360 and GiMS?
-
4.2 NCRs Status?
-
4.3 NCR Register?
5. Documentation and Reports
-
Final Phase of the Project
-
5.1 Have quality packs been reviewed and compiled as per the ITP?
-
5.2 Have all relevant paper documents been scanned and kept in an effective manner?
-
5.3 Is a person appointed to track and manage snagging, NCRs and Handovers?
-
5.4 Have all snags, NCRs and Handovers been closed out effectively?
-
5.5 Have arrangements been made to deliver the O&M Manual to the client?
-
5.6 Glass replacement strategy plan approved by client.
-
5.7 Structural Silicone Glazing control (training and records available and sample records)?
-
5.8 Are all areas handed over and accepted? (Register)
-
5.9 After sales involvement (are After Sales being integrated into project and aware of issues)?
-