Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
PV Array Test
-
Test instrument
String 1
-
Array Module
-
Array Quantity
-
Array Parameters - Voc (STC)
-
Array Parameters - Isc (STC)
-
String overcurrent protective device - Type
-
String overcurrent protective device - Rating (A)
-
String overcurrent protective device - DC Rating (V)
-
String overcurrent protective device - Capacity (kA)
-
String Wiring - Type
-
String Wiring - Phase CSA (mm2)
-
String Wiring - Earth CSA (mm2)
-
String Test - Voc (STC)
-
String Test - Isc (STC)
-
String Test - Irradiance
-
Polarity Check
-
Array Insulation Resistance - Test Voltage (V)
-
Array Insulation Resistance - Pos - Earth (MΩ)
-
Array Insulation Resistance - Neg - Earth (MΩ)
-
Earth Continuity (where fitted)
-
Array Isolator - Rating (A)
-
Array Isolator - Rating (V)
-
Array Isolator - Location
-
Array Isolator - Functional Check
-
Inverter - Make
-
Inverter - Model
-
Inverter - Serial Number
-
Inverter - Functional Check
String 2
-
Array - Module
-
Array - Quantity
-
Array Parameters - Voc (STC)
-
Array Parameters - Isc (STC)
-
String over-current protective device - Type
-
String over-current protective device - Rating (A)
-
String over-current protective device - DC Rating (V)
-
String over-current protective device - Capacity (kA)
-
String Wiring - Type
-
String Wiring - Phase CSA (mm2)
-
String Wiring - Earth CSA (mm2)
-
String Test - Voc (STC)
-
String Test - Isc (STC)
-
String Test - Irradiance
-
Polarity Check
-
Array Insulation Resistance - Test Voltage (V)
-
Array Insulation Resistance - Pos - Earth (MΩ)
-
Array Insulation Resistance - Neg - Earth (MΩ)
-
Earth Continuity (where fitted)
-
Array Isolator - Rating (A)
-
Array Isolator - Rating (V)
-
Array Isolator - Location
-
Array Isolator - Functional Check
-
Inverter - Make
-
Inverter - Model
-
Inverter - Serial Number
-
Inverter - Functional Check
Commissioning Checks
-
Generator’s Installation satisfies the requirements of BS7671 (IET Wiring Regulations).
-
Suitable lockable points of isolation have been provided between the PGMs and the rest of the Generator’s Installation.
-
Labels have been installed at all points of isolation in accordance with EREC G99.
-
Interlocking that prevents PGMs being connected in parallel with the DNO’s Distribution Network (without synchronising) is in place and operates correctly.
-
Balance of Multiple Single Phase PGMs. Confirm that design of the Generator’s Installation has been carried out to limit output power imbalance to below 16 A per phase, as required by EREC G99.
-
Installation complies with cyber security requirements
-
The Interface Protection settings have been checked and comply with EREC G99.
-
The system successfully synchronises with the DNO’s Distribution Network without causing significant voltage disturbance
-
The system successfully runs in parallel with the DNO’s Distribution Network without tripping and without causing significant voltage disturbances.
-
The system successfully disconnects without causing a significant voltage disturbance, when it is shut down.
-
Interface Protection operates and disconnects the DNO’s Distribution Network quickly (within 1 s) when a suitably rated switch, located between the PGM and the DNO’s incoming connection, is opened.
-
The PGM remains disconnected for at least 20 s after switch is reclosed.
-
Loss of tripping and auxiliary supplies. Where applicable, loss of supplies to tripping and protection relays results in either PGM or Generating Unit forced trip or an alarm to a 24 hour manned control centre.
DC side – Inspection & Test Requiurements
-
General check to confirm system complies with relevant standards.
-
PV voltage suitable for location
-
Components selected and erected to suit location and external influences
-
Roof and building penetrations weatherproof (where applicable)
-
Verification of protective measures against shock.
-
Parts selected and erected so as to minimise the risk of earth faults and short circuits.
-
Identification if the inverter has at least simple separation.
-
Identification of any functional earthing
-
Presence of earth insulation resistance detection and alarm system
-
Presence of earth residual current monitoring detection and alarm system
-
String cables sized appropriately for prospective fault currents
-
String/array over current protective devices correctly specified and installed
-
Check of any functional earth connections
-
Check functional earth fault interrupters are fitted (where required)
-
Check of any earthing and/or equipotential bonding
-
Verify wiring loops minimised
-
SPDs, where fitted, suitable selected and erected
-
Measures in place to protect long cables
-
All d.c. components rated for d.c. and for voltage and current maxima
-
Wiring selected and erected to suit external influences (wind, UV etc.)
-
String/array isolation and disconnection devices correctly specified and located
-
Plug and sockets are of same type and correctly mated
-
Means of isolating inverter provided on AC side
-
AC Isolators correctly connected
-
Inverter parameters correctly specified on AC side
-
RCDs correctly selected and installed (where fitted) on AC side
-
All parts correctly labelled and suitably durable
-
Schematics and other signs suitably displayed
-
Test to ensure the continuity of earthing and/or equipotential bonding conductors (if fitted)
-
Connection to main earthing terminal verified
-
Test to ensure that all strings and arrays are correctly marked and connected
-
Test to ensure that all strings are correctly connected within a combiner box (if fitted)
-
Test to ensure that module strings are correctly installed and that the right number of modules are connected within a string
-
Test to ensure that there are no major faults within a string
-
Short-circuit and operation test options presented
-
Tests to ensure switchgear operated correctly
-
Tests to ensure inverters operating correctly
-
Test the string VOC
Evidence Requirements
-
MPAN (electricity Bill)
-
Existing Renewables - Manufacturer & Model and<br>Date of install
-
Location of lockable isolation switch
-
Panel Model & Serial Number
-
How many panels installed?
-
Generation meter make & model
-
Battery installed?
-
Battery Make, Model and Serial Number
-
Fuse Board
-
New system clearly shown (isolation switch etc)
-
Generation Meter (working)
-
Panels
-
Engineer sign off