Title Page

  • Project

  • Date of inspection

  • Block/Level/Plot No.

  • MAST Interiors Site Manager Signature

  • Date

  • Main contractor Site Manager Signature

  • Date

Quality Check

Pre CloseUp inspection

  • The latest Drawings & Specification have been used

  • Visual inspection of the design information, provided drawing number & Recorded in the QA

  • Both M&E handovers have been issued and the Principal contractor has confirmed the Close up

  • Hand over received and recorded in the QA

  • All Noggins have been installed in line with the project specification

  • Bathrooms, Kitchens, Radiators, etc.Visual inspection & photographic records provided in the QA

  • External, partition walls and SVP INSULATION installed correctly in line with the project specification

  • Visual & Project specification check and Photographic records provided in the QA

  • VCL - vapour barrier installed correctly with the correct size overlaps and seals

  • Visual & Project specification check and Photographic records provided in the QA

CloseUp

  • Correct type of wall plasterboard have been used as per project specification

  • Visual inspection and Photographic records provided in the QA

  • The correct screws are used and at the designed centers

  • Visual inspection and Photographic records provided in the QA

  • Wall lining Dot&Dab as per project specification

  • Visual inspection of full dabs around sockets, corners, windows, ceiling line & recorded in the QA

  • All corners and reveals checked and are square and plumb

  • Visual & Dimensional checks carried out and recorded in QA

  • Fire TAPE (jointing) above ceiling level checked and installed correctly

  • Visual inspection & recorded in the QA

  • Mastic to service penetrations have been sealed in line with the project specification

  • Visual inspections & Photographic records provided in the QA

  • Setting out of the ceiling grid incorporates all services and ceiling height to the latest design specification

  • Visual inspection and Photographic records provided in the QA

  • Correct type of ceiling plasterboard have been used as per project specification

  • Visual inspection & recorded in the QA

  • Plot cleared of all access materials & waste ready for hand over

  • Visual inspection & Photographic records provided in the QA

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.