Information

  • Locomotive Number

  • Conducted on

  • Location
  • Auditor

Inspection Items

  • 1. Was locomotive properly cleaned?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 2. Does the handbrake apply and release and is the inspection date current & recorded on back of Blue form? (228.46 & 232.105)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 3. Is the FRA blue cab form and air card properly completed, signed, and dated? (229.23) Where applicable 184 day Q sticker must be applied to blue form holder and Mechanical Department Log Form # 480-9000007-1 must be completed.

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 4. Do bell (229.45) and wiper motors operate properly (X-2400-08)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 5. Do the radio and HTD operate properly (229.45)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 6. Was a standing air brake test performed and did it pass? (229.59) (A/C cuts in at 130 - cuts out at 140 / min. 10 lb. increase; 229.49)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 7. Were the alerter or deadman pedal qualified? (229.23)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 8. Seats - Inspect all cab seats for defects and proper operation. (229.119)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 9. Is toilet & toilet compartment clean and odor free (toilet operates as intended)? (229.139)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 10. Is toilet compartment properly vented? (229.139)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 11. Are all fluid levels correct? (1700-01)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 12. Were any oil, water, fuel (229.45) or exhaust leaks detected? (X-1700-03)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 13. Was the APU/ERM properly set up and fluids correct? (E-500-12)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 14. If locomotive was shopped for low water problems, was the low water button tripped to verify engine protector shutdown? (E-500-12)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 15. Were all covers (229.41), fasteners, safety chains (229.119), and doors in (229.45) place and secured?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 16. Was the sanding system operational (229.131) with no holes in the hoses?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 17. Do all lights (229.125 & 229.127) and alarms function properly (229.115 & 229.101)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 18. Are all Annunciator lights off? (troubleshoot/reset as required)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 19. Are cab heaters, toilet heaters, (229.119) (Sept - April) and air conditioners operating properly? (April - Sept)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 20. Is the unit clear of low voltage grounds? (use 6W test light) (X-6800-21)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 21. If equipped with dynamic brake system, perform static test. (232.109)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 22. Does RPM increase while advancing throttle positions. (X-1700-02)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 23. Does the unit load forward and reverse? (X-1700-02)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 24. Verify the ground relay cut-out switch is sealed and the counter zeroed? (NA if software controlled through MMI)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 25. Was the unit self load tested to qualify volts, amps, and the horsepower?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 26. If shopped for hot engine, were the temperature controllers, fans, and shutters qualified? (run through 2 cooling cycles) (NA for GE's)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 27. If applicable, was the cab signal equipment set up and self-tested properly?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 28. If equipped, are the traction motor, GRP, DB cut-out and cab signal cut-out switches sealed?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

Bottom Inspection Items

  • 29. Do all the handrails, standards, grab irons, and steps have the proper clearance, no defects, and OK for service? (231.29 & 231.30)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 30. Was flange lube stick system serviced & magazines aligned? (X-1400-17)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 31. Are all fuel monitors, fuel sensors, hoses, and Snyder adapters operational? (Monitors range within 40 gallons) (X-2100-08)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 32. Are the main reservoir drain valves/spitters set to automatic and is condensation drained from the main reservoir and final filters? (229.46)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 33. Does the air dryer cycle properly & are the indicator eyes blue? (229.46)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 34. Are the brake shoes properly aligned (229.57), not worn (1700-01), and is the piston travel correct (1700-01/229.55)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 35. Are all springs, snubbers, liners, and pads in good condition and pilot height correct. Inspect that shocks are free of leaks (229.65)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 36. Are coupler (231.144.C1), throwers, knuckles, bails, and cut levers operating properly and in adjustment (231.30)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 37. Are all T/M covers (229.41), T/M leads, and axle alternator wiring properly secured (229.45)?

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 38. Are MU cables installed, properly secured to the hangers, and not chafing? (229.89)

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

  • 39. List separately any identified FRA defect not covered in this checklist.

  • Reviewed With Title / Name

  • Corrective Action

  • Completion Date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.