Information
-
Locomotive Number
-
Conducted on
-
Location
-
Auditor
Inspection Items
-
1. Was locomotive properly cleaned?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
2. Does the handbrake apply and release and is the inspection date current & recorded on back of Blue form? (228.46 & 232.105)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
3. Is the FRA blue cab form and air card properly completed, signed, and dated? (229.23) Where applicable 184 day Q sticker must be applied to blue form holder and Mechanical Department Log Form # 480-9000007-1 must be completed.
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
4. Do bell (229.45) and wiper motors operate properly (X-2400-08)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
5. Do the radio and HTD operate properly (229.45)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
6. Was a standing air brake test performed and did it pass? (229.59) (A/C cuts in at 130 - cuts out at 140 / min. 10 lb. increase; 229.49)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
7. Were the alerter or deadman pedal qualified? (229.23)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
8. Seats - Inspect all cab seats for defects and proper operation. (229.119)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
9. Is toilet & toilet compartment clean and odor free (toilet operates as intended)? (229.139)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
10. Is toilet compartment properly vented? (229.139)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
11. Are all fluid levels correct? (1700-01)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
12. Were any oil, water, fuel (229.45) or exhaust leaks detected? (X-1700-03)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
13. Was the APU/ERM properly set up and fluids correct? (E-500-12)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
14. If locomotive was shopped for low water problems, was the low water button tripped to verify engine protector shutdown? (E-500-12)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
15. Were all covers (229.41), fasteners, safety chains (229.119), and doors in (229.45) place and secured?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
16. Was the sanding system operational (229.131) with no holes in the hoses?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
17. Do all lights (229.125 & 229.127) and alarms function properly (229.115 & 229.101)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
18. Are all Annunciator lights off? (troubleshoot/reset as required)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
19. Are cab heaters, toilet heaters, (229.119) (Sept - April) and air conditioners operating properly? (April - Sept)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
20. Is the unit clear of low voltage grounds? (use 6W test light) (X-6800-21)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
21. If equipped with dynamic brake system, perform static test. (232.109)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
22. Does RPM increase while advancing throttle positions. (X-1700-02)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
23. Does the unit load forward and reverse? (X-1700-02)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
24. Verify the ground relay cut-out switch is sealed and the counter zeroed? (NA if software controlled through MMI)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
25. Was the unit self load tested to qualify volts, amps, and the horsepower?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
26. If shopped for hot engine, were the temperature controllers, fans, and shutters qualified? (run through 2 cooling cycles) (NA for GE's)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
27. If applicable, was the cab signal equipment set up and self-tested properly?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
28. If equipped, are the traction motor, GRP, DB cut-out and cab signal cut-out switches sealed?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
Bottom Inspection Items
-
29. Do all the handrails, standards, grab irons, and steps have the proper clearance, no defects, and OK for service? (231.29 & 231.30)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
30. Was flange lube stick system serviced & magazines aligned? (X-1400-17)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
31. Are all fuel monitors, fuel sensors, hoses, and Snyder adapters operational? (Monitors range within 40 gallons) (X-2100-08)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
32. Are the main reservoir drain valves/spitters set to automatic and is condensation drained from the main reservoir and final filters? (229.46)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
33. Does the air dryer cycle properly & are the indicator eyes blue? (229.46)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
34. Are the brake shoes properly aligned (229.57), not worn (1700-01), and is the piston travel correct (1700-01/229.55)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
35. Are all springs, snubbers, liners, and pads in good condition and pilot height correct. Inspect that shocks are free of leaks (229.65)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
36. Are coupler (231.144.C1), throwers, knuckles, bails, and cut levers operating properly and in adjustment (231.30)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
37. Are all T/M covers (229.41), T/M leads, and axle alternator wiring properly secured (229.45)?
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
38. Are MU cables installed, properly secured to the hangers, and not chafing? (229.89)
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date
-
39. List separately any identified FRA defect not covered in this checklist.
-
Reviewed With Title / Name
-
Corrective Action
-
Completion Date