Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location
  • Level

  • Elevation/Section

Brick Slips

  • Have all pre closeup inspections been carried out by Jessella & BYUK ?

  • Have all Horizontal rails being installed as per design?

  • Have the Horizontal rails being installed with the correct<br>spacing between mid rails and from starter/top rail?

  • Has the Siderise Intumescent Strip being installed where<br>necessary?

  • Have the correct colour bricks been used in this area?

  • Have the brick slip tiles been installed following manufacturers guidelines, following the required pattern and design?

  • Have the reveals been built as per design?

  • Are all aluminium bricks in the correct positions (lights, RWP)?

  • Are movement joints in the correct location and width of joints 10mm ?

  • Are bed / perpend joints uniform and within NHBC tolerances ?

  • Is the area clear of any significant cracks, chips and marks ?

  • Has a Side Rise intumescent sealant been added in the brick slip extrusion profile niche? (Brick slips in front of Cavity Barriers only!)

Sign Off

  • Jessella

  • Client

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.