Has the correct type being used in this area?
-
Have all cavity barriers been installed as per the fire strategy layout<br>drawings?
-
Have all cavity barriers been installed using the correct fixings?
-
Have all cavity barriers been installed tightly abutted and to manufacturers guidelines?
-
Have all cuts and joints been sealed using a foil tape?
-
Have all vertical cavity barriers been installed under compression?
-
Have all horizontal cavity breaks been installed to allow the correct airflow? (note: 50mm unless design states otherwise)
-
Have the Cavity Barriers to SFS walls been fixed into studs?