Title Page
-
Site:
-
Location
-
Created by
-
Specification:
First and second fix
-
Confirm MEP overhead is complete and sign-<br>off before ceiling framing. <br>
-
Confirm MEP rough opening layout <br>complete.
-
Confirm the wall are fire taping and MEP <br>caulking completely.
-
Confirm specification
-
Confirm drawing
-
Check that correct pattresses have been provided for M&E fixing
-
Check all required hangers are provided, securely fixed and vertical and with appropriate centres in accordance with manufacture guidance.
-
Check the ceiling is fixed to correct line and level.
-
Check the ceiling insulation installed correctly
-
Check if the correct plasterboard and number of layers are fixed following manufacturer guidance.
-
Check the distance between screws/ and right fixings as per manufacture guidance.
-
Access panels provided at specified location
Sign off
-
All evidences and action closed by:
-
Left area tidy for following trades
-
Date closed