Title Page

  • Project Title (Job type - Name - Address)

  • Conducted on

  • Prepared by

  • Location

External Work

  • Is the heat pump level

  • Is the base suitable, Solid level base to take weight, or on gravel soak away

  • Are the external pipe extrusions sealed

  • Have clearances been met as per manufactures instructions

  • Are pipes correctly insulated bonded and sealed with 19mm wall suitable for external conditions, i.e primary pro, HT or external trunking

  • Anti-vibration feet or wall brackets with Anti-vibration mounts installed

  • Isolation valves on Flow and return for ASHP including strainer valve

  • Does the condensate terminate correctly/soak away to prevent future hazards

Internal Checks

  • Are internal pipe intrusions sealed

  • Is the pipe work insulated and sleeved the entire depth of the wall

Removal of old sytem

  • Evidence of boiler removal and previous flue hole brick up

  • Confirm that the gas pipe has been capped correctly to GSE regs

  • Has the previous heating electrical supply been isolated and made safe?

  • Confirm removal of existing HW cylinder and cold water poly tanks

  • Let by and tightness test recorded on TPI and sent to manometerresults@lowribeckfield.co.uk

  • Record Gas safety report of gas installation remaining (certificate on TPI)

Cylinder installation

  • Isolation valve installed above control group

  • Confirm Discharge D1 is max 600mm to tundish

  • Confirm Discharge D2 is min 300mm before first bend

  • Picture of termination of D2 pipework inc required cage

  • Picture of Cylinder and surrounding pipework, Lagging and insulation done correctly to a high standard

Commissioning

  • System parameters set up, Flow temperatures set up with weather curve

  • System flushed

  • System balanced, vented and ensured system gets to temperature

  • Cylinder hot water temperature set to min 50℃ (legionnaires cycle set up if below 55℃)

  • System controls, thermostats, programmers and safety controls all explained to the client/homeowner/tenant/landlord (picture taken of programmer set up)

  • Benchmark filled out for heatpump & recorded

  • Benchmark filled out for cylinder and recorded

  • ASHP data badge

  • Cylinder data badge filled out

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.