DGP0153 SITE PROJECT QUALITY AUDIT Rev 0 - 20/10/2016
STANDARD INFORMATION
-
BRANCH MANAGER
-
CONTRACT MANAGER
-
SITE MANAGER / SUPERVISOR
-
SITE ADDRESS
-
CLIENT / PRINCIPAL CONTRACTOR
-
JOB NUMBER
QUESTIONS
-
Have we received a Notice to Commence and has it been Acknowledged?
-
Is the Site Accommodation in a tidy state?
-
Is there a Site Diary?
-
If so, is the Site Diary up to date?
-
Does the Site Diary state Weather Conditions?
-
Does the Site Diary state where Resources are allocated on the project?
-
Does the Site Diary Record any Delays or Stoppages we have incurred?
-
Is there a Main Contract Programme?
-
Have we produced and issued a Dodd Group Programme?
-
Are we issuing 2 Weekly / 4 Weekly Progress Reports against this Programme?
-
Do the Progress Reports clearly identify if and why we are not on programme?
-
Are Trade Quality Plans being adhered to (i.e. Checklists/Sign Offs for each stage of the works, Floor/Wall/Ceiling Closures etc.)?
-
Is there a Procurement Schedule?
-
If so, are we Meeting Procurement Dates (look for Order Numbers)?
-
Is there an up to date RFI Schedule?
-
If so, have we advised them of any outstanding RFI's?
AUDIT OBSERVATIONS
-
ADDITIONAL COMMENTS