Information

  • Document No.

  • Job No. and Floor Level

  • Conducted on

  • Superintendent name

  • GC Representative Signing Off

Slab Pre Pour.

  • Are all safety rails in place and at proper height ?

  • Are ladders placed for proper egress during and after slab pour ?

  • Has slab elevation been verified by field engineer?

  • Are all kickers installed and nailed on edge forms ?

  • Have edgeforms been aligned with a string line ?

  • Is the condition of the plywood on tables and fillers acceptable for exposed ceilings ?

  • Is chamfer installed in all required locations ?

  • Does edge form line up with the top of columns from floor below ?

Balconies

  • Is drip strip installed correctly ?

  • Is curb installed at correct height and width ?

  • Is depression installed straight and secured from movement ?

  • Is all Formwork on balconies in good condition ?

Slab pre pour. Pour A

  • Have all items above been checked for slab pour 1? If no explain below

Slab pre pour. Pour B

  • Have all items above been checked for slab pour 2? If no explain below

Slab pre pour. Pour C

  • Have all items above been checked for slab pour 3 ? If no explain below

Post Pour

  • Has concrete leakage on floor, around columns and walls been removed and disposed of?

  • Has concrete seepage from slab bulkhead been removed before it sets up ?

Slab post pour. Pour A

  • Have all items above been checked for slab pour 1? If no explain below

Slab post pour. Pour B

  • Have all items above been checked for slab pour 2 ? If no explain below

Slab post pour. Pour C

  • Have all items above been checked for slab pour 3 ? If no explain below

Vertical pre pour

  • Do new control lines match with previous pour slab edges and floor openings ?

  • Are exterior columns plumb and line up with slab edge and columns below ?

  • Has Grade in forms been checked ?

  • Are Dummy ties installed correctly and secured to prevent movement ?

  • Are reveals installed correctly and secured to prevent movement ?

  • Have all forms been checked for proper bolts, pins, clamps and braces ?

Vertical post pour

  • Have all columns been rechecked for plumb after concrete placement?

  • Have walls been rechecked for plumb and realigned with string line after concrete placement ?

  • Is all remedial work on outside face of exterior columns done while the deck is in place ?

  • Have all chamfer strips and fins been removed from columns after stripping ?

  • Was concrete seepage under forms removed as soon as forms were stripped?

Vertical post pour. Pour A

  • Have all items above on pour 1 vertical been checked ? If not explain below.

Vertical post pour. Pour B

  • Have all items above on pour 2 vertical been checked ? If not explain below.

Vertical post pour. Pour C

  • Have all items above on pour 3 vertical been checked ? If not explain below.

Reshore floors

  • Are all permanent safety rails, hole covers (labeled) and ladders reinstalled properly?

  • Is all trash and formwork debris been consolidated and ready for removal ?

  • Have all wood splinters nails and concrete fins been removed from ceiling ?

  • Is all SPS work complete on this level ?

  • Are all Reshores removed ?

  • Is all SPS material removed from floor ?

  • Is the condition of forms providing a concrete finish that is acceptable in exposed areas ?

  • Is floor clean and swept ?

  • Is floor signed off by General Contractor ?

  • When all items are complete and signed off by GC for this level save and export to qc@southernpan.com

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.