Title Page
-
Quality inspection report
-
Jobsite
-
Conducted on
-
Prepared by
-
Location
Equipment: Furnace,A/C coil
-
Installed properly sloped and secured
-
Flue Venting and drain lines ran and hooked up to provided drain
-
Drain pan and wet switch required
Duct work
-
All ducts is installed and insulated properly
-
Heat registers screens and ceiling boots installed with bat wings
-
Flex ducts installed correctly and strapped every 4'
-
Wall stacks is secured and framing strapped
Exhaust fans,range and dryer venting
-
All fans are installed
-
All fans are vented and outside hoods is installed with proper paper and quick flash behind
-
Dryer vent is hooked up and screen is removed in outside hood
-
Range vent is installed with outside termination
HWH
-
Sleeve, vent pipes or quick flash installed
Zoning
-
By-pass and zoning dampers installed and marked
Filters,f/a, filters box
-
All required filters installed
Make up air
-
120volt timer, motor, damper and current sensor provided