Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Subgrade has had chip seal applied
-
Is Formwork checked with survey, adequately supported, mortar tight and deboned ?
-
Is pour area is and free from loose or foreign material?
-
Surface is in a damp condition and free from pounding water?
-
Is 150mm deep Subbase achievable throughout
-
Pre-Pour inspection conducted by Main Contractor
-
Weather for paving to start:<br>- Air temp between 5 degrees and 36 degrees<br>- Not raining nor imminent
-
Concrete deposited and spread uniformly without segregation
-
All loads formed within appropriate time <br>- 90min for air temp <30degrees<br>- 45min for air temp >30degrees
-
Concrete temp when sampled is between 10 degrees and 32 degrees
-
The Subbase surface finish has a uniform, dense, compact finish
-
Hessian drag finish applied
-
Curing compound applied at required rate and has created a continuous and unbroken film over the Subbase
-
Has the start-end/stop-end been checked for straight edge and alignment conformance
-
Has all waste/spoil been cleaned up