Title Page

  • Site Name

  • Date

  • Stantec Representative(s) on site

  • Prepared by

  • Meeting Attendances

  • Weather Conditions Today

Today's Activities and Tomorrow's Plan

  • Crew 1

  • Crew Activity in Shift

  • Borehole Reference

  • Borehole Depth at end of shift (m)

  • Borehole Reference

  • Borehole Depth at end of shift

  • Trial Pits Completed in shift

  • Trial Pits left open at end of shift

  • Trial Pits that did not achieve specified depth

  • Did anything occur today that could have impact on DATA QUALITY or was OUTSIDE the contract specification?

  • Details

  • Did anything occur today that could have impact on PROGRAMME?

  • What is the Plan for tomorrow?

  • Are there any planned activities / locations that requires the Investigation Supervisor to be at the Crew1 location tomorrow to oversee?

  • Details

  • Are there any technical clarification or instruction the Contractor is waiting on from the Investigation Supervisor that will be required for tomorrows shift?

  • Details

  • Is there any other information waiting on from other parties that is required to avoid delays?

  • Details

  • Any OTHER expected delays on Programme tomorrow?

  • Details

  • Crew 2

  • Crew Activity in Shift

  • Borehole Reference

  • Borehole Depth at end of shift (m)

  • Borehole Reference

  • Borehole Depth at end of shift

  • Trial Pits Completed in shift

  • Trial Pits left open at end of shift

  • Trial Pits that did not achieve specified depth

  • Did anything occur today that could have impact on DATA QUALITY or was OUTSIDE the contract specification?

  • Details

  • Did anything occur today that could have impact on PROGRAMME?

  • What is the Plan for tomorrow?

  • Are there any planned activities / locations that requires the Investigation Supervisor to be at the Crew1 location tomorrow to oversee?

  • Details

  • Are there any technical clarification or instruction the Contractor is waiting on from the Investigation Supervisor that will be required for tomorrows shift?

  • Details

  • Is there any other information waiting on from other parties that is required to avoid delays?

  • Details

  • Any OTHER expected delays on Programme tomorrow?

  • Details

  • Crew 3

  • Crew Activity in Shift

  • Borehole Reference

  • Borehole Depth at end of shift (m)

  • Borehole Reference

  • Borehole Depth at end of shift

  • Trial Pits Completed in shift

  • Trial Pits left open at end of shift

  • Trial Pits that did not achieve specified depth

  • Did anything occur today that could have impact on DATA QUALITY or was OUTSIDE the contract specification?

  • Details

  • Did anything occur today that could have impact on PROGRAMME?

  • What is the Plan for tomorrow?

  • Are there any planned activities / locations that requires the Investigation Supervisor to be at the Crew1 location tomorrow to oversee?

  • Details

  • Are there any technical clarification or instruction the Contractor is waiting on from the Investigation Supervisor that will be required for tomorrows shift?

  • Details

  • Is there any other information waiting on from other parties that is required to avoid delays?

  • Details

  • Any OTHER expected delays on Programme tomorrow?

  • Details

Logging Shed

  • Logger 1

  • Borehole Reference Logging

  • Depths Logged

  • Any significant zones of low recovery?

  • Details

  • Zones of unexpected ground conditions, potential geological hazards or anything the logger would like to flag?

  • Details

  • Any unresolved questions or queries from the logger to the Investigation Supervisor team?

  • Details

  • Logger 2

  • Borehole Reference Logging

  • Depths Logged

  • Any significant zones of low recovery?

  • Details

  • Zones of unexpected ground conditions, potential geological hazards or anything the logger would like to flag?

  • Details

  • Any unresolved questions or queries from the logger to the Investigation Supervisor team?

  • Details

  • Logger 3

  • Borehole Reference Logging

  • Depths Logged

  • Any significant zones of low recovery?

  • Details

  • Zones of unexpected ground conditions, potential geological hazards or anything the logger would like to flag?

  • Details

  • Any unresolved questions or queries from the logger to the Investigation Supervisor team?

  • Details

  • Has there been a Core pick-up and transport to the Contractors Laboratory today ?

  • Which Boreholes / Samples ?

Data Management

  • Logs Issued to Investigation Supervisor today?

  • Logs:

  • Logs returned to Contractor with comments?

  • Logs:

  • General comments on logging, sampling and AGS data issued by the Investigation Supervisor?

  • Details

  • Blank Schedules issued today to Investigation Supervisor by the Contractor for scheduling testing?

  • Exploratory Locations:

  • Testing Schedules issued to Contractor

  • Schedule Number(s)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.