Client Information
-
Please enter Riverton Electrical Job number
-
Enter client name here.
-
Client / Site if different from above
-
Conducted on
-
Prepared by
-
Please check all applicable boxes
- Kitchen Renovation
- Laundry/Bathroom Renovation
- Jobbing/Service work
- Testing, tagging, checks
-
Please enter quick Job description.
-
Location
-
Is it Three phase or Single phase?
-
Overhead supply or underground supply
-
Is the underground pillar situated on this property?
-
Is the overhead supply from a western power pole or intermediate pole?
-
Please enter the meter number here
-
YOU MUST ENTER A METER NUMBER !!!!!
Final Checklist
-
Are ALL power and lighting circuits protected by at LEAST 2 RCD's
-
Have all new power points been checked and tripped by RCD tester at max 30mA?
-
If lights were installed are all lights working?
-
Were any of the lights installed recessed downlights?
-
Have we installed signage in the roof space as per AS3000:2007 4.5.2.3.2
-
Have all GPO and Light switch covers been accounted for and presented to customer?
-
Has all rubbish been swept up and taken away or placed in bin?
-
Have all appliances installed been tested and are working?
-
Have we installed any Dual Gas/Electric Aplliances? (this includes hotplates and upright stoves)
-
Have we installed an isolation switch as per AS3000 Clause 4.18.1
-
Has the client received a safety certificate
-
Has client received final invoice
-
How would the client like to pay?
-
Please list any items that have not been completed or require a return visit.
-
Please take photo's of job before leaving. (At minimum switchboard and work completed)