Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Previous Project Inspection
-
Has the last job-site inspection been reviewed in preparation for this inspection?
-
Are there any outstanding corrective actions to be taken?
General Conditions
-
Perimeter fence in good condition?
-
Project signage posted?
-
Danger and caution tape maintained?
-
Adequate toilet facilities?
-
Drinking water provided?
Housekeeping
-
Appearance of job-site neat and orderly?
-
Passageways and walkways clear?
-
Projecting nails removed or bent over?
-
No slips or trip hazards
Power and Hand Tools
-
Tools and cords in good condition?
-
All mechanical safeguards in place?
-
Right tools used for the job at hand?
-
PPE appropriate for the tools used?
Ladders
-
Ladders secured to prevent movement?
-
Ladders used are in good condition?
-
Ladders used properly?
Fall Protection
-
Guardrails installed and maintained in good condition?
-
Personal fall arrest equipment in good condition?
-
Fall arrest equipment used properly?
-
Excavations guarded and marked?
-
Fall protection equipment inspected?
Scaffolding
-
Scaffolds erected competent person and clearance cert displayed
-
Scaffold planks have proper overlap?
-
Guys, ties and braces in place at 4:1 rule?
-
Guardrail system in place?
-
Access laddesrs in place?
-
Cross bracing in place?
Excavations & Shoring
-
Shoring of adjacent structures adequate?
-
Banks of excavation sloped or shored correctly?
-
Spoil piles at least 2m from boundary
-
Competent person on site while excavating
PPE
-
Safety glasses used by employees?
-
Proper hand protection in place?
-
Proper footwear?
-
Hearing protection used?
-
Respiratory protection used?
Electrical
-
RCD tested every 28 days
-
All extension cords 3 wire type, in good condition with ground pins?
-
All power boards contain RCD test switch.
-
All switch boards are earthed and door remains closed?
Stairways
-
Treads and landings acceptable?
-
Handrails installed?
-
Temp lighting in stairways acceptable?
-
Housekeeping?
Material Handling
-
Material stacked, racked, etc...?
-
Materials stored properly and out of weather
Other Observations
-
Project employee/supervision concerns
-
Follow up/pre-planning items
-
Issues/comments
-
Rivergumhomes Supervisor/Construction Manager