Information
-
Site
-
Conducted on
-
Prepared by
-
Personnel
-
Location
QUALITY
-
Current drawings being used
-
Superseded drawings marked, clipped together and separate current drawings
-
Document register in file & matches documents on site
-
Inspection test plan is up to date
-
Evidence of one ITP follow through
-
Site administration SF 4.8 - 1.1a signed off
-
Non-conforming items in quarantine area, tagged and recorded
-
Calibration dates on equipment current
HSEQ CONTROL (OSH Act 1984 Section 19, OSH Regulations 1996 3.1-3.2, Environmental Protection Act 1986 Section 72)
-
Current Revision of SMP/EMP/Risk Register in site file
-
HSEQ Master form SF 4.4-1.4 Operating Procedures REVs up to date
-
Site administration documents SF 4.8-1.1B revision current and correct revisions of documents in file
-
Start up risk assessment available and relevant actions signed off
-
Induction register is up to date
-
Daily sign in register being used
-
Pre shift agenda being conducted daily
-
Blood Alcohol Content (BAC) screens done daily
-
Supervisor OHS weekly checklist being used
-
Safety, Environmental & Quality policies are displayed
-
JSEAs developed as per SMP
-
Work conducted as per JSEA and all workers signed on ( RJV & Subcontractor)
-
Safe Work Method Statement available and operators signed on (RJV & Subcontractor)
-
Fuel truck in designated handstand area where practical
-
Dust suppression in use
-
Dust is managed so that no visible dust is along the boundary
-
Permits and licenses in place
-
Implementation on controls from two items under high risk register
EMERGENCY ( OSH Regulations 1996 3.8-3.12)
-
First aid box is on site where signs indicate
-
First aid box is fully stocked
-
Trained first aiders are on site and are identified
-
Evacuation plan is displayed
-
Assembly muster point sign is up
-
Emergency contact number is displayed
-
Fire extinguisher in compound available and in date
WORKSITE MANAGEMENT (OSH Regulations 1996 3.1)
-
Site communication methods displayed (UHF Channels)
-
Site fencing is intact (if main contractor)
-
Construction signage at interfaces between works and public roads / access
EARTHWORKS HAULAGE
-
Haulage route width ample for two way haulage (approx 15m)
-
Haulage route two way traffic are adequately separated by windrows where practicable
-
Haulage route segregated from other works eg) away from workers on the ground and other machines
-
Haulage route free from potholes and rocks
-
Haulage route declines and bends minimised as far as practicable
-
Haulage route edges adjacent excavations are built up and windrows sufficient to axel height
-
No unauthorised vehicles or subcontractors using haul route
-
Giveaway protocol followed
TRAFFIC MANAGEMENT (PUBLIC AREAS)
-
Works undertaken on/or adjacent to public road has a TMP
-
Traffic management on site matches TMP (if applicable)
-
Traffic management plan is relevant to the stage of works
-
A daily inspection log is conducted by a BWTM (minimum 3 times a day)
-
Signs are legible to road users and in reasonable condition
-
The road speed is reduced to 40km where workers on foot are within 1.2m to the traffic and delineation installed
-
The road speed is reduced to 60km where workers on foot or plant are within 1.2m to 3m of the traffic able area with no physical barrier. Delineation is installed
-
Excavation near public road adequately protected for workers and public vehicles
-
Stop/go personnel ticketed
PUBLIC SAFETY ( OSH Act 1984 Section 20-22, OSH Regulations 3.17)
-
Site entrance signage in place (if principle contractor)
-
Construction materials kept within the workplace
-
Any risk of objects falling on members of the public
-
Any risk of trip hazards to the public
-
Public access controlled
-
Site perimeter fencing or barricades erected
-
Warning signs in place and relevant to risk
BARRICADES (OSH Act 1984 Section 20, OSH Regulations 1996 3.6-3.8, 3.11 & 3.17)
-
Works adjacent to public thoroughfare de-marketed/ barricaded
COMPOUND (OSH Regulations 1996 3.6-3.8, 3.11 & 3.17)
-
Compound signage in place
-
Compound fence in tact
-
Site containers are neat and tidy (floors free of spills and obstruction)
-
Toilets facilities are clean and well maintained
-
No smoking stickers outside crib room and office
-
Designated smoking areas enforced
-
Litter is placed in bins; bins are emptied regularly
CHEMICAL AND HAZARDOUS SUBSTANCES (OSH Regulations 1996 Part V)
-
Chemicals are storied in bunded area
-
Chemicals are stored in original or clearly labeled containers
-
Spill cleanup equipments available
-
Hydrocarbons stored in areas of containment
-
MSDS are available for all chemicals
PERSONAL PROTECTIVE EQUIPMENT WORN (OSH Regulations 1996 3.32, 3.40-3.44)
-
High visibility clothing worn
-
Hearing protection
-
Footwear
-
Eye protection
-
Head Protection worn where risk of being hit in the head
-
Sunscreen
LIGHT VEHICLES (OSH Regulations 1996 3.1)
-
Light vehicles in work area have two way communication
-
Rotating yellow/orange light working
-
Seat belts in good condition and in use
-
Non-work LV's parked in designated parking area and not in construction work areas
-
Pre starts being completed on RJV vehicle
-
First aid box required
WELDING AND CUTTING (OSH Regulations 1996 3.27)
-
Hot works permit used
-
Equipment in good operating condition
-
Work area is clear of combustible material
-
Operator using PPE
-
Correct type of fire extinguisher near by
-
Gas cylinder secure and upright
-
Gas lines protected and in good condition
-
Double flash back arrestors
-
Welding/cutting screens used
ELECTRICAL (OSH Regulations 1996 3.59-3.65, 4.38 & AS/NZS 3012:2012)
-
Genset for compound is earthed with copper rod
-
Permanent live boards locked
-
Covers used correctly
-
Temporary boxes numbered
-
Insulated tie bars in place
-
Electrical tools and leads tagged, RCD used
-
Electrical leads raised
OVERHEAD POWERLINES (OSH Regulations 1996 3.64)
-
Electrical clearances over main access roads to job e-mailed to sub contractors
-
Permit to work under lines available and implemented. JSA in place
-
Danger zone clearances measured and displayed
EXCAVATION (OSH Regulations 1996 3.109-3.113)
-
Excavation code of practice information
http://www.commerce.wa.gov.au/worksafe/PDF/Codes_of_Practice/code_excavation.pdf -
Excavation Safe slopes
-
Excavation sides battered / benched to code of practice
-
Where batters and benching cannot meet the Excavation Code of Practice adequate shoring to be erected
-
Adequate access to excavation
-
Adequate barriers and signs on excavation
-
Spoils being used as windrow of adequate size and protects workers from driving into excavation
-
Adequate distance between passing traffic and excavation edge
-
No excavated material or other loads are placed near the excavated area where there is risk that the sides of an excavation may collapse or plant/load may fall into excavated area.
STOCKPILES
-
Stockpiles are at the correct height ratio for soil types / sheer faces knocked down at end of the day
-
Stockpiles are not creating blind spots or hazards to traffic on site
LIFTING AND CHAINS
-
List chains serial number and last test date
-
Chain has identification tag and Working Load Limits (WLL)
-
Load being lifted does not exceed Working Load Limit of weakest point in lifting system
-
Weight of load is evenly distributed on sling legs
-
Chain is free of twists and protected from sharp corners of the load
-
Worker using chains that has no engineered approved lifting points is a ticketed dogman
-
Chain links are not bent, gouged or stretched and safety latch if applicable is functional
-
Slings are not torn or defective
TAGGING PROCEDURES (OSH Regulations 1996 4.38)
-
Danger tags & out of service tags available and being used
-
Out of service equipment is in quarantined area and isolated from use
PLANT EQUIPMENT (OSH Regulations 1996 Part IV)
-
Pre-start books completed on a sample of plant
-
Observation of pre-start being conducted
-
Rotating yellow/orange light working
-
Reverse beepers working
-
Fire extinguisher in date and good order
-
Seat belts in good condition and in use
-
Two way radio in working order
-
Steps and grab rails in good order
-
Hire plant in good condition
RETAINING WALLS
-
Excavations in front of retaining walls are risk assessed and authorised by Project Manager/Structural Engineer (OP 4.18-3.23A)<br>Controls from Engineer/PM are reflected in JSEA.<br>Workers are signed onto JSEA
-
Mobile plant clearance area away from wall
-
Safety fencing if required
GENERAL
-
Add media
-
Add media
CORRECTIVE ACTION (IMMEDIATELY)
-
Supervisor items to action
-
HSEQ items to action
-
Workshop items to action
-
Subcontractor (Drainage Supervisor to sign off if available)
-
Subcontractor (Wall Builder supervisor to sign off if available)
-
Subcontractor (other - list company name) Supervisor to sign off if available
CORRECTIVE ACTIONS WITHIN 7 DAYS (That require close out confirmation by HSEQ Coordinator)
-
Corrective action 1
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 2
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 3
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 4
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 5
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 6
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
CORRECTIVE ACTIONS GREATER THAN 7 DAYS (close out to be determined by HSEQ Management on corrective actions register)
-
Corrective action 1
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 2
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 3
-
Corrective action to be actioned by
- supervisor to action
- project manager to action
- workshop to action
- HSEQ to action
- subcontractor drainer to action
- subcontractor wall builder to action
- subcontractor -other to action
- n/a
-
Corrective action 4
SIGN OFF
-
RJV On site representative
-
Auditor