Information
-
Audit Title
-
Conducted on
-
Prepared by
-
Business Unit Manager
-
Operations Executive
1. Quality Control
1.1 Summary of Concrete Related Records
-
Equipment Calibration Records (QP 7.6.4)
-
Yearly Inspection of Cube Moulds (YQC 4)
-
Monthly Checking of Thermometers (MQC 2)
-
Monthly Water Meter Check (MQC 12)
-
Checking of Mass Meters (WQC 1)
-
Weekly Admixture Check (WQC 2)
-
Aggregate Grading Analysis (WQC 3 & 4)
-
Aggregate gradings meeting the required specification.
-
Fineness Modulus Tracking (WQC 5)
-
SCC Viscosity Check (WQC 6)
-
Cube and Slump Test Results (DQC 1)
-
Cube results meet the required specification
-
Moisture Control (GPC 4)
-
Steam Temperature Control (GPC 6)
-
Acid Insolubility Test Result (GPC 9)
-
6 month bases
-
Curing Bath Temperature Record Sheet (GPC 7b)
-
Bought in Cementitious Material Inspection (SQC 1)
-
Bought in Aggregate Inspection (Visual)
-
Cube Failure Checklist (SQC 21)
-
Only required if cubes failed
-
Additional Observations
1.2 Testing of Aggregate
-
Sampling done in accordance with SWI 7.4.3-01
-
Sieve analysis done in accordance with SWI 7.4.3-01
-
Sieves are clean and in good working condition (SWI 7.6-09)
-
Additional Observations
1.3 Testing of Hardened Concrete
-
Cube specimens are being crushed on a non floated surface
-
Cube specimens are tested at the correct load rate
-
Load rate range 0.3MPa/s +- 0.1 (SANS 5863:2006) new is 0.6mpa/s +-0.2mpa
-
Cube specimens are free from any severe defects
-
Cube specimens are the correct dimension and shape (5 random cubes were selected)<br>
-
Dimensions: 90-110mm & 1mm between each face. Perpen. 0.5mm;
-
Cube moulds are cleaned, oiled and stored neatly
-
Additional Observations
2. RS Production
2.1 Batching and Mixing
-
Cross-contamination of aggregate between adjacent storage bins
-
Contamination of aggregate from underlying soil
-
Contamination of aggregate from organic matter (such as leaves and twigs)
-
Water in the hopper pit is minimised
-
Adequate drainage in and around aggregate storage bins
-
Identification of cementitious storage (silo) are in place
-
Identification of aggregate bins are in place
-
Comments
-
Photo/s of Housekeeping
-
All the control boxes are locked and correctly labelled
-
Side = 5 mm, Bottom = 10 mm max.
-
Side scraper is the correct distance from the mixer side wall
-
Ask for the tool used to test these distances
-
Side scraper is clean and in good working condition?
-
Mixer arms are the correct distance from the mixer floor
-
Mixer arms are clean and in good working condition?
-
Mixer door (gate) is sealing correctly (no loss of fines)
-
All mix designs in use are the latest revision and have been approved
-
Mixer operator has made a moisture adjustment
-
Look to see if any signs of moisture adjustment has been made and ask why not?
-
Materials are being batched accurately (SWI 7.5.1-02).
-
10kg for cement and stone, 5kg for sand and fly ash, SANS = 2% cementitous and 3% for aggregate
-
Admixture dispenser is dosing accurately (Max 5%)
-
Water, admixture, and cementitious valves and gates are functioning properly
-
Concrete mix is homogeneous before being discharge from the mixer
-
Significant spillage during the discharge process
-
Segregation of the mix during discharge
-
Additional Observations
2.2 Sampling and Testing of Concrete
-
Concrete has been sampled in accordance with SWI 7.5.1-09
-
Slump/Flow test has been done in accordance with SWI 7.5.1-09
-
Correct procedures being done when the slump falls outside the specified limits
-
Cube specimens have been made in accordance with SWI 7.5.1-09
-
Additional Observations
-
Add media
2.3 Casting and Finishing
-
Segregation of the mix during transport
-
Significant spillage during the transport process
-
Segregation of the mix during casting
-
Significant spillage during the cast process
-
Concrete has be effectively compacted
-
Products are floated/striked off after casting
-
Products are finished off after floating
-
Excess concrete cleaned off the moulds after casting
-
Products were protected immediately after floating
-
Additional Observations
-
Add media
2.4 Curing
-
Pre-steam time was at least 30 minutes after casting
-
Actual time recorded was
-
Has the steam been utilised correctly
-
Curing temperature measure correctly
-
Products allowed to cool-down for 30 minutes prior to stripping
-
Additional Observations
-
Add media
2.5 Product Quality
-
Defects not impairing the functional use or expected life of a
precast concrete product shall be considered minor defects.
Minor defects may be repaired by any method that does not
impair the product. -
Honeycombing on products
-
Severity of honeycombing
-
Refer to SWI 7.5.1/08 for repairing concrete products
-
Blowholes on products
-
Severity of blowholes
-
Less than 5 mm deep in isolated areas will be acceptable. Blowholes should not affect the sealing of rubber ring joints.
-
Bleeding on products
-
Severity of bleeding
-
Refer to SWI 7.5.1/08 for repairing concrete products. Sand streaks shall not be accepted.
-
Cracking on products
-
Refer to SWI 7.5.1/08 for repairing concrete products
-
Overall Quality of Repair Work
-
Comments on Repair Work
-
Photos of Repair Work
-
Handling and stripping damage
-
Additional Observations
3. Culverts Production
3.1 Batching and Mixing
-
Cross-contamination of aggregate between adjacent storage bins
-
Contamination of aggregate from underlying soil
-
Contamination of aggregate from organic matter (such as leaves and twigs)
-
Water in the hopper pit is minimised
-
Adequate drainage in and around aggregate storage bins
-
Identification of cementitious storage (silo) are in place
-
Identification of aggregate bins are in place
-
Comments
-
Photo/s of Housekeeping
-
All the control boxes are locked and correctly labelled
-
Side = 5 mm, Bottom = 10 mm max.
-
Side scraper is the correct distance from the mixer side wall
-
Ask for the tool used to test these distances
-
Side scraper is clean and in good working condition?
-
Mixer arms are the correct distance from the mixer floor
-
Mixer arms are clean and in good working condition?
-
Mixer door (gate) is sealing correctly (no loss of fines)
-
All mix designs in use are the latest revision and have been approved
-
Mixer operator has made a moisture adjustment
-
Look to see if any signs of moisture adjustment has been made and ask why not?
-
Materials are being batched accurately (SWI 7.5.1-02).
-
10kg for cement and stone, 5kg for sand and fly ash, SANS = 2% cementitous and 3% for aggregate
-
Admixture dispenser is dosing accurately (Max 5%)
-
Water, admixture, and cementitious valves and gates are functioning properly
-
Concrete mix is homogeneous before being discharge from the mixer
-
Significant spillage during the discharge process
-
Segregation of the mix during discharge
-
Additional Observations
3.2 Sampling and Testing of Concrete
-
Concrete has been sampled in accordance with SWI 7.5.1-09
-
Slump/Flow test has been done in accordance with SWI 7.5.1-09
-
Correct procedures being done when the slump falls outside the specified limits
-
Cube specimens have been made in accordance with SWI 7.5.1-09
-
Additional Observations
-
Add media
3.3 Casting and Finishing
-
Segregation of the mix during transport
-
Significant spillage during the transport process
-
Segregation of the mix during casting
-
Significant spillage during the cast process
-
Concrete has be effectively compacted
-
Products are floated/striked off after casting
-
Products are finished off after floating
-
Excess concrete cleaned off the moulds after casting
-
Products were protected immediately after floating
-
Additional Observations
-
Add media
3.4 Curing
-
Pre-steam time was at least 30 minutes after casting
-
Actual time recorded was
-
Has the steam been utilised correctly
-
Curing temperature measure correctly
-
Products allowed to cool-down for 30 minutes prior to stripping
-
Additional Observations
-
Add media
3.5 Product Quality
-
Defects not impairing the functional use or expected life of a
precast concrete product shall be considered minor defects.
Minor defects may be repaired by any method that does not
impair the product. -
Honeycombing on products
-
Severity of honeycombing
-
Refer to SWI 7.5.1/08 for repairing concrete products
-
Blowholes on products
-
Severity of blowholes
-
Less than 5 mm deep in isolated areas will be acceptable. Blowholes should not affect the sealing of rubber ring joints.
-
Bleeding on products
-
Severity of bleeding
-
Refer to SWI 7.5.1/08 for repairing concrete products. Sand streaks shall not be accepted.
-
Cracking on products
-
Refer to SWI 7.5.1/08 for repairing concrete products
-
Overall Quality of Repair Work
-
Comments on Repair Work
-
Photos of Repair Work
-
Handling and stripping damage
-
Additional Observations
4. Sign Off and Summary
4.1 Sign Off
-
Auditor