Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Job Information

  • OSHA 300 forms complete and posted from February 1 - April 30

  • Team Huddles up to date and complete?

  • Daily stretches being completed by all crews?

  • Emergency phone numbers posted?

  • OSHA and DOL posters posted?

  • "Safety Time-Outs" performed?

  • Work areas properly signed and barricaded?

  • Safety Data Sheets filed and accessible?

  • First-aid kit fully stocked with non-expired medicine?

  • Traffic control zones set up properly and maintained?

  • Corrective Action:

Housekeeping

  • Work areas neat?<br>

  • Projecting nails and screws bent over or removed?

  • Waste containers provided and being used?

  • Containers clearly labeled?

  • Passageways and walkways clear?

  • Corrective Action:

Fire Prevention

  • Adequate fire extinguishers , checked and accessible?

  • "No smoking"signs posted and enforced near flammables?

  • Corrective Action:

Electrical

  • Extension cords with bare wires or missing ground plugs taken out of service?

  • Ground fault circuit interrupters being used?

  • Temporary lighting where needed and compliant?

  • Terminal boxes equipped with required covers?

  • Corrective Action:

Hand,Power & Powder Actuated Tools

  • Hand tools inspected regularly?

  • Guards in place on machines?

  • Correct tool being used for the job at hand?

  • Operators of powder actuated tools trained?

  • Corrective Action:

Fall Protection

  • Safety rails and cables secured properly?

  • Safety harness worn properly?

  • Employees exposed to fall hazards tied off?

  • Employees below protected from falling objects?

  • Corrective Action:

Ladders

  • Ladders extended at least 36" above landing?

  • Ladders are secure to prevent slipping,sliding or falling?

  • Ladders with split or missing rungs taken out of service?

  • Stepladders used in fully open postion?

  • No step at top two rungs of stepladder?

  • Corrective Action:

Scaffolding

  • All scaffold inspected daily?

  • Erected on sound rigid footing?

  • Tied to structure as required?

  • Guardrails,intermediate rails, toe boards and screens in place?

  • Planking sound and sturdy?

  • Proper access provided?

  • Employees below protected from falling objects?

  • Corrective Action:

Floor & Wall Openings

  • All floor opening(s) planked over and labeled "hole" or barricaded?

  • Perimeter protection in place?

  • Deck planks secure?

  • Materials stored away from edge?

  • Corrective Action:

Trenches,Excavation & Shoring

  • Compentent person identified and present?

  • Excavation Checklist(s) and Daily Trenching Log(s) filled out prior to starting excavation?

  • Excavations are shored and sloped back?

  • Materials are stored at least 2' away from trench?

  • Ladders provided every 25' in trench?

  • Equipment is at safe distance from edge of trench or excavation?

  • Corrective Action:

Confined Space

  • All confined spaces labeled?

  • Employees working in confined spaces properly trained?

  • All Confined Space documentation (including permits) filled out?

  • Air monitoring taking place?

  • Attendant in place and focused on task?

  • Rescue/ retrieval system in place?

  • Corrective Action:

Material Handling

  • Materials properly stored and stacked?

  • Employees using proper lifting techiques?

  • Proper number of workers for each operation?

  • Corrective Action:

Welding And Burning

  • Gas cylinders stored up right and capped?

  • Proper separating distance between fuels and oxygen?

  • Goggles, sheild and proper PPE used?

  • Fire extinguishers readily accessible?

  • Hoses and regulators in good condition?

  • Corrective Action:

Cranes

  • Crane inspections complete and up-to-date?

  • Crane operators log up to date?

  • Operator is familiar with load chart?

  • Hand signal charts on crane?

  • Outriggers extended and swing radius barricade in place?

  • Employees kept from under suspended loads?

  • Tag lines used to guide loads?

  • Chains and slings inspected and tagged as required?

  • Overhead hazards marked and proper clearance maintained?

  • Corrective Action:

Mobile Equipment(Manlifts, Forklifts ect.)

  • Equipment inspected and maintained?

  • Machinery equipped with back up alarm and functioning properly?

  • Operators trained for specific equipment?

  • Operators manual, safety manual and warning labels in place?

  • Corrective Action:

Concrete Construction

  • Employees are protected from cement dust?

  • Rebar bent over or capped to prevent impalement hazard?

  • Designated concrete wash out area being utilized?

  • Wash station readily accessible?

  • Corrective Action:

Personal Protective Equipment

  • Safety glasses being worn?

  • Respirators used when required? Proper respirator documentation available?

  • Hard hats being worn?

  • Task specific PPE worn as required?

  • Employees wearing appropriate gloves for the task?

  • Hearing protection being worn where required?

  • Corrective Action:

  • General Comments:

  • Safety Representative

  • Project Manager/ Superintendent

  • Sketches:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.