Quality Control Audit / Slab on Grade
-
Conducted on
-
Location
-
Auditor
Project & Concrete Design information
-
Project Number
-
Enter date
-
Area / location of Pour.
-
Adds ( calcium, plasticizers, etc.)
-
Product name.
- Non Calcium chloride
- Super P
- Med P
- NCAA
- Retardent
- Daraset (winter)
- Fibers
-
Do we have a proper place for storing concrete cylinders.
Sign off Area
-
Special Inspector : Name
-
Company Name
- Terracon
- Bruan
- Shive Hattery
- Brian
-
City / County inspector sign off.
-
Plumbing sign off:
-
Rebar installer sign off.
-
Mechanical sign off.
-
Electrical sign off.
-
Form work / Finishers sign off.
Slab on Grade checklist
-
Verify fill materials required and proctors are completed and compaction verified.
-
Add media
-
Verify inspector has signed off on sub grade prior to placing vapor barriers, rebar, mesh etc.
-
Add media
-
Verify vapor barrier requirements for type, and req'd taping & lap.
-
Add media
-
Are construction joints required to have keyway / reinforcing?
-
Have we verified that that keyways and dowels are in per spec?
-
Add media
-
Verify that all rebar, dowels and mesh are installed as required. Check for proper clearances. ( ie. Chairs, Doby, inserts)
-
Add media
-
Are Embeds required in this pour. (Block outs, keyed joints, floor drains, expansion joints, bond breakers etc)<br>
-
Did we confirm type used is correct for each location?
-
Add media
-
Did we check orientation & placement?
-
Add media
-
Are embeds going to be checked during pour as well. (By who?) ( example floor drain level and correct elevation)
-
Add media
-
Are floor drains / clean outs being marked or flagged to locate while pouring?
-
Add media
-
Are anchor bolts required in this pour?
-
Checked proper size of anchor bolts
-
Add media
-
Checked bolt pattern and or bolt setting template?r
-
Add media
-
Proper bolt projection & bolts are plumb?
-
Add media
-
Has Access/ hoisting been determined?
-
How will concrete be conveyed to area?
- wheel barrow
- power buggies
- pump
- crane bucket
- truck
-
Do we have a safe route & access planned during concrete placement? ( barricades, caution tape, other)
-
Is manpower & equipment secured for placement & finishing for a pour of this size?
-
Add media
-
Slab placement equipment in place? ( laser screed, Power screed, Hand screed
-
Add media
-
Slab cutting & joint pattern determined prior
-
Add media
-
Verify saw cutting for the day of pour? If yes, do we have this equipment in place?
-
Add media
-
Is there any special floor flatness or finish requirements.
-
Is the floor flatness documentation plan in place?
-
Add media
-
Have we ensured that everyone understands those plans & requirements
-
Level of floor finish understood by all? ( burned, broomed, etc)
-
Add media
-
Finishing equipment in place? ( trowel machines, edgers, fuel)
-
Add media
-
Have we confirmed the curing method required?
-
Curing method materials & equipment needed in place?
-
Add media
-
Are all concrete delivery & inspections properly documented and scheduled?
-
Add media
-