Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Check all decking for loose sheets & use self tapping screws to secure overlaps
-
Check all decking for missing or loose clips
-
Check all post bracket nuts and bolts for tension
-
Check all main cables clips are 5/8" & make sure they are tightened
-
Check all shackle plates for loose nuts and bolts
-
Check all tie-ups to ensure they are equally tensioned and the platform is level
-
Check all rigid tie-up assembly connections. Ensure all nuts & jamb nuts are installed appropriately
-
Check all rigid tie-up connections to existing steel & cable/decking ensuring all attachments are secure
-
Check all beam flange clamp hangers for secure attachment
-
Check all perimeter railing posts for stability
-
Check all perimeter 1/4" cable for tension (top rail shall not deflect below 39" above deck)
-
Check all perimeter cable for 1/4" cable clamps
-
Check all perimeter posts for caps
-
Check platform for remaining parts and debris
-
Check all connections with conformance with the plans