Compliance Checklist
Equipment Details
Switchboards
-
Where temporary switchboards installed?
-
Location of temporary boards installed
Temporary Lighting
-
Was any temporary lighting installed?
-
Location and type of temporary lighting installed
Emergency Lighting
-
Was any emergency lighting installed?
-
Location and type of emergency lighting installed.
Generator
-
Was a one or more temporary generators installed?
-
Location and description of temporary generator(s) installed.
Test Report (ticking the boxes indicates a pass)
-
Earthing System Integrity
-
Insulation Resistance
-
Correct Circuit Connection
-
Residual Current Device Operation
-
Polarity
-
Fault Loop Impedance (if necessary)
Installation (ticking the boxes indicates a pass)
-
Construction Wiring labelled at maximum 5 metre intervals
-
Construction Wiring encased in conduit to prevent mechanical damage
-
Lamps in luminaires shall be protected against mechanical damage
Temporary Power Board(s) Report (ticking the boxes indicates a pass)
-
Source of Supply identified
-
Board Number identified
-
Main Circuit identified
-
Main isolating switch is labelled
-
Circuits are secured to prevent accidental or deliberate re-energisation
-
Energised parts protected
-
External metal work not energised
-
Temp Board has an insulated Tie Bar
-
Temp Board has minimum IP 23 Rating
-
Temp Boards have a safe means of entry for leads (insulated bush)
-
Temp Boards are secured taking into account unexpected external forces (mechanically fixed to wall, floor or post)