1.0 - Site File Compliance
-
1.1 - Is the pre start checklist in place ?
-
1.1.1 - Has the Pre Start Checklist been filled in ?
-
1.2 - Is the Method Statement & Risk Assessment in place ?
-
1.2.1 - Has the Method Statement & Risk Assessment been signed by all operatives
-
1.2.2 - Have the Method Statement & Risk Assessment been reviewed within the last 6 Months and or still adequate and task/risk specific? <br>
-
1.3 - Have the Sign in sheets been filled in by all operatives on a daily basis ?
-
1.4 - Are Daily Diaries being completed on a daily basis ?
-
1.5 - Are tool box talks being carried out each week ?
-
1.6 - Have All scaffolds been inspected in the past 7 days ?
-
1.6.1 - Are Scaffold Inspection sheets kept in the site file ?
-
1.7 - Have all Harness inspections been carried out in the last 7 days ?
-
1.7.1 - Are harness inspection records being maintained in the safety file ?
-
1.8 - Are time sheets being kept in the site file ?
-
1.9 - Are Previous site safety audits being stored in the site file?
-
1.10 - Are Anchor tests reports being stored in the site file?
-
1.11 - Are Training records being updated and stored in the site file?
-
1.12 - Is the Accident / Incident / Near miss paperwork up to date ? <br>
-
1.12.1 - Has their been any Accident on the project since last visit?
-
1.13 Has the LOLER register been maintained?
-
1.14 - Has the HAVS register Been maintained?
-
1.15 - Has the PPE register been maintained ?
-
1.16 - Are Emergency Procedures & First Aid Arrangements in place ?
-
1.17 - Are the company Policies and procedures in the site file ?
-
1.17.1 - Is their an up to date copy of Insurance in the site file ?
-
1.18 - Has PAT testing been carried out in the last 3 months ?
-
1.19 - Are the most recent revision of drawings onsite ?
-
1.19.1 - Has the Temporary works register been maintained?
2.0 - Foundations
-
2.1 - Ground conditions can take the weight of the scaffolding
-
2.2 - No evidence of sinkage
-
2.3 - Scaffolding not erected on manhole covers
-
2.4 - Scaffolding not erected over excavations
-
2.5 - scaffolding not erected near trenches
3.0 - Footings ( Base Plate & Sole Boards )
-
3.1 - Are sole boards he correct dimensions
-
3.2 - Are base plates fitted correctly
-
3.3 - The footings are not damaged
4.0 - Standards
-
4.1 Are standards correctly spaced ( as per design or TG20 )
-
4.2 - Are couplers ( sleeves ; joints ) staggered ?
5.0 - Ledgers
-
5.1 - Are he ledgers Horizontal ?
-
5.2 - Are joints staggered ?
6.0 - Transoms
-
6.1 - Are Transoms horizontal?
-
6.2 - Have right angle couplers used (as required) ?
-
6.3 - Are transom spacing correct for support of the board and as per design ?
-
6.4 - tubes are at least 50mm pass the coupler?
-
6.5 - is the working platform wide enough and to design ?
7.0 - Edge Protection & General Protection
-
7.1 - top Handrail fitted at correct height?
-
7.2 - Intermediate rails fitted at the correct height?
-
7.3 - toe boards fitted to all elevations including haki staircases
-
7.4 - Gates and operable?
-
7.5 - Edge protection secured and undamaged. <br>
-
7.6 - Trapdoors fitted in platforms were applicable?
8.0 - Boards
-
8.1 are boards free from all defects?
-
8.2 - Are all boards still in the correct position and not be tampered by others on site ?
-
8.3 - are boards secured where applicable?
-
8.4 - Are boards correctly supported by the Transoms?
-
8.5 - Are boards placed so they don't cause slips , trips and falls ?
9.0 - Bracing
-
9.1 Facade bracing been fitted correctly?
-
9.2 - Ledger bracing been fitted correctly?
-
9.3 - Plan bracing fitted where applicable
-
9.4 - Are correct couplers fitted?
10.0 - Ladders
-
10.1 - Are the ladders adequate length and raise above the platform 1.00mtrs?
-
10.2 - Are ladders correctly secured?
-
10.3 - Are all ladders undamaged?
-
10.4 - have ladders been inspected within the last three months?
-
10.5 - Are all ladders set at the correct angle i.e 1 to 4
11.0 - Security and Protection
-
11.1 - is public protection adequate?
-
11.2 - is the means to prevent public access adequate ?
-
11.3 - safe passage available to the public
-
10.4 Signage adequate and fixed into place?
12.0 Ties
-
12.1 - Are ties fitted to right angle couplers ,
-
12.2 - is pull testing up-to date as per company policy ( 10 percent) ?.
-
12.3 - Is he tie certification in the site health and safety folder?
-
12.4 - Have ties been fitted as per scaffolding design ?
13.0 Miscellaneous
-
13.2 scaffolding structure has been designed and erected to the specification ?
-
13.3 - SWL of scaffolding has not been exceeded?
-
13.4 - monarflex / debris netting fitted correctly and tidy ?
Quality Inspection Check sheet
-
Are Exclusion zones being maintained ?
-
Have all Actions been closed out from the previous visit , if not detail those outstanding!
-
Have all personnel completed Alandale Plant & Scaffolding induction?
-
Does the site have adequate cover on site when Alandale Site Supervisor is off?
-
Are harness been worn correctly by operatives ?
-
Does the lorry have a lifting plan when on site , does he require one ?
-
Is house keeping on site to a good standard ?
-
Is the welfare facilities on site to a good standard and conform to the HSAW act ?
-
Warning signs have been erected i.e locations and elevations.
-
Are all scaffolding operatives been issued with tether tools ?
14.0 - Details of issues arising from this scaffolding inspection
-
14.1. Recommendations/Personal Responsible /Target Date
15.0 - details of actions to be taken.
-
15.1 - Details of actions taken by competent persons to rectify issues/ date / completed