Inspection check list
Activity: Finals.
-
Rehang doors into decorated frames.
-
Check latch / lock actions.
-
Install 2nd fix ironmongery to doors in accordance with door ironmongery check list.
-
Internal flat doors single. No of Doors:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
-
Internal flat doors double. No of Doors:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Mirror Cabinet Doors.
-
Check line and level.
-
Check no damage.
-
Check mirror screw caps fitted.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Check Line, Level and Position.
-
Check towel rail.
-
Check toilet roll holder.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Bath Panel.
-
Check no damage.
-
Check screw caps fitted.
-
Tidy Dry - check position and operation.
-
Shower Curtain - check position and operation.
-
Check all doors for signs of swelling due to damp/moisture penetration after rehang.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor