Information
-
Product Audit - Stream Crossing
-
Document No.
-
Observer
-
Conducted on
Chainage
-
General information:
-
Line
- West Derwent River
- Derwent River Crossing
- Main Line 1
- Main Line 2
- Main Line 3
- Main Line 4
- White Kangaroo Road Spur
- Prossers Road Spur
- Orielton South Branch
- Brinktop Road West Spur
- Brinktop Road East Spur
- Shrub End Road Spur
- Table Hill Spur
-
Chainage to: Chainage from:
-
Easting
-
Northing
Safety
-
Is there a JSEA on-site?
-
Is safety signage been displayed?
-
Are identified hazardous trees been managed?
-
Is minimum on-site safety standards been maintained e.g. (PPE, flashing beacon, reverse parking)
Pre start
-
Is there an approved Erosion and Sediment Plan (ERSED) for pipe crossing works?
-
Is there an approved Environmental Plan (CEP / EMP) for pipe crossing works?
-
Have all CEP or EMP boundaries and exclusion zones been flagged prior to crossing works commencing?
-
Have all ERSED control measures been installed prior to crossing works commencing?
Weed Management
-
Have all construction machinery been inspected to confirm they are weed free?
Clearing at water courses
-
Have disturbance limits within the riparian zone been minimised and managed as per an approved FPP or in accordance with the contractors CEP or EMP?
-
Have marked trees been felled parallel to the construction corridor and without falling into the watercourse?
-
Has the cleared vegetation been stockpiled as far as practicable away from the riparian watercourse zone or as specified within an FPP, CEP or EMP?
-
Are all identified sediment and erosion control measures effective around water course approaches and stream banks?
Erosion & Sediment Control Measures
-
Have all geo textile silt fences been secured in place with star pickets or other means and are being maintained to retain their effectiveness?
-
Has water runoff from the pipe crossing works area been diverted into either a settling pond, sediment trap or through vegetated ground to stop sediment entering the waterway?
Watercourse Crossing Method Option 1 (above ground crossing)
-
Has trenching ceased within 2m from the edge of the waterway?
-
Have all footings and structures been kept away from the channel confines and streambed?
-
Have all machinery been prevented from entering the waterway?
Watercourse Crossing Method Option 2 (below ground crossing)
-
Have sediment traps been installed downstream of the works?
-
Has stream flow been diverted around the excavation site and then re-inserted back into the main flow of the channel downstream?
-
Has the removed stream bed material been stockpiled in the same order as it was excavated, including river rock?
-
Has the stream bed material been returned back to its original profile?
-
Is is trench and hydrostatic water being discharged through sediment filters?
Pipe laying in watercourse
-
Has the pipe section designated for the crossing been fabricated prior to trenching completion to enable rapid installation?
-
Has the pipe been encased in concrete to correct design specification prior to backfilling?
Reinstatement in watercourses
-
Have appropriate bank stabilisation measures been implemented such as (slope stabilisation, revegetation, soil coverings, rip-rap and armouring, check dams, sediment traps and vegetation filters)?
-
Have in stream surface layer of either cobbles, course gravels or rock been replaced / introduced over the disturbed area and placed so it is not likely to act as a barrier to the passage of aquatic fauna?
-
If required, have sandbags, gabions or other means of scour protection been installed to confirm to the natural contours?
Notes
Sketches
-
Add drawing
Photos
-
Add media
Sign Off
-
Add signature