Initial Visit
-
Is there a clear set of notes on file from the inspection. Do they include the names of the parties at the meeting and record what matters to the customer. Site plan only required when needed
CDM
-
Is there a completed HS-IFC on file?
Schedule
-
Is a completed spec on file inc:<br>- Part 1A or 1B Site Specific Requirements<br>- Part 3 Schedule of Repairs<br>- Part 4 Schedule of Works(inc. schedule of finishes)<br>- Residents Paper & Colour choices<br>- Summary Page & Form of Tender
SLA
-
Has the specification and CDM documents been issued within 3 days of the visit?
Procurement
-
Is there a FirstPort procurement report and tender analysis on file, issued within 3 days of receipt of tenders?
PCM
-
Are PCM minutes on file, do they record the start date and have they been issued to all parties within 3 days of the meeting?
Start on Site
-
Did a call take place from the Hub to the House Manager on the first day of the works to confirm the works had started.
Works - Internal Decorations
-
Did a wallpaper specification meeting take place with confirmation sent to Contractor and FirstPort?
Works - External Decorations
-
Did a Site visit take place to check the preparation works before decoration and is the clearly recorded on file?
Works - Final Visit
-
Did a final visit take place, with notes on file and a snagging list prepared and issued to all parties within 3 days of the visit?
Snagging
-
Did a call take place between the Hub and House Manager to confirm that all snagging was completed?
Cost Control
-
Did costs come in within 105% of procurement costs?
Rectification
-
Did a call take place at the end of the defects period between the Hub and the House Manager and were FirstPort advised to release the retention?
Fees
-
Has the correct fee(s) been issued? (CDM charged hourly, recorded on TDRS)