Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
team audited
Site details
-
Site location
-
SOE Number
-
Inspected by
-
Inspected on
Inspection
-
Is breathing apparatus out, ready for use and in date?
-
Voltstick available and in working condition?
-
Has the service been disconnected from the meter as per SGN work procedures?
-
Has the service been disconnected from the main as per SGN work procedures?
-
Please detail the method used for the service entry point (inserted/house entry tee/cellar entry)
-
If inserted, has the annulus been sealed with an approved sealant (grout)?
-
Has the service entry been carried out as per SGN work procedure?
-
Has a meter box been installed?
-
Has an ECV been fitted correctly? (accessible, handle down for off position etc)
-
White bonnet and sleeve fitted?
-
Has the service been purged and tested as per SGN work procedure? (e.g.100mb for 5 minutes)
-
Has the test been recorded with time, date and test details?
-
Is the service diameter the correct size for the length of the service?
-
Is electrofusion method being used?
-
Are fittings fused correctly? (check alignment and fusion points etc)
-
Are alignment clamps / top tee clamps available and in date?
-
Is the evidence that alignment clamps have been used? (clamps and fittings should be marked with pen to evidence their use)
-
Will the service have the correct depth of cover once reinstated?
Sign off
-
Date and time
-
Inspector