Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Project No:
-
Catchment:
-
Sub Catchment:
-
CIZ No.
1. Planning and Approvals
-
All Plans/Permits valid and onsite - ie. Power Company, Council or VicRoads MOA
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
2. Construction Documentation
-
SWMS relevant for specific site
-
Excavation Permit
-
Confined Space Entry Permit
-
Valid Q form
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
3. Construction Plant and Equipment
-
Daily pre-start checklists completed for all plant
-
CSE equipment satisfactory
-
Plugs (not damaged)
-
Hoses (no leaks)
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
4. Service Location and Protection
-
"Dial Before You Dig" information onsite<br>
-
All known existing services have been located and proved prior to work commencing
-
Minimum clearance maintained as per WSA 07-2006
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
5. Traffic Management
-
Set up as per site Traffic Management Plan
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
6. Inspection of Materials
-
Pipe and fittings conform to specifications and are in new condition
-
Pressure rating PN16/SDR11, Pipe colour black
-
Quarry certificates submitted for bedding and backfill materials
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
7. Establish Environmental Controls (as per TMP)
-
Silt fencing set up where required
-
Silt traps employed where required
-
Parra webbing erected around protected trees/vegetation
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
8. Pipe Alignment
-
As per Construction Drawings
-
Survey has marked out alignment prior to excavation
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
9. Trench
-
Sufficient traffic management and signs around excavation
-
Adequate fall from heights protection installed where required
-
Quarry products stored correctly
-
Spoil stored correctly or removed from site
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
10. Butt Welding
-
3 test welds/operator tested in accordance with ISO13953:2001 by NATA registered laboratory
-
Test results received and have passed
-
Welding machine calibration certificate valid
-
PE pipe ends cleaned prior to welding
-
Welded pipe cooled for correct length of time
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
11. Laying Pipe
-
Minimum cover achieved as per WSA 07-2006
-
Tracer wire installed with pipe and to standard
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
12. Electro Fusion Jointing
-
Ensure pipe is round
-
Outside of pipe is scraped down and cleaned with alcohol wipes
-
No water present around join while welding is in progress
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
13. Bedding of Pipe for Open Cut
-
Bottom of trench is free from sharp obstructions
-
Min 100mm compacted sand on bed of trench
-
Min 150mm compacted sand surrounding pipe
-
Marker Tape installed on top of bedding material (min 150mm above pipe)
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
14. Compaction and Backfill
-
Backfill to MRWA Specification No. 04-03.1 or to Road Authority's requirements
-
The Road Authority's requirements shall take precedence if they exceed the requirements of the MRWA Specification.
MRWA Specification for roadways:
- up to 1.5m deep - 20mm Class 2 Plant Mixed Wet Mix Crushed Rock
- Over 1.5m - top 600mm to be 20mm Class 2 Plant Mixed Wet Mix Crushed Rock, 20mm Class 4 Crushed Rock for remainder.
- Excavations in Footpaths - 20mm Class 4
- Backfill placed in 200mm layers and compacted to required density 95% AS. -
Compaction Test Report/s received
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
15. Acceptance Testing
-
Pressure testing for Pressure Sewer (hydrostatic)
-
Pressure Testing for gravity system (vacuum or low air pressure testing)
-
Deflection testing (only for gravity - to be done 14 days after compaction has been completed)
-
CCTV received and satisfactory
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
16. Reinstatement
-
Construction Impact Zones and affected work areas restored to condition prior to commencement of works
-
All surplus material removed from site
-
Date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Trinh
NOTES AND COMMENTS
South East Representitive
-
Add signature