1. Planning and Approvals
-
All Plans/Permits valid and onsite - ie. Power Company, Council or VicRoads MOA
-
Select date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Tranh
- Tony Dibben
- John Di Cosmo
2. Construction Documentation
-
SWMS relevant for specific site and activities
-
Flushing Point constructed as per Standard Drawings SEW_PSS_004 or SEW_PSS_008
-
Isolation Valve constructed as per Standard Drawing SEW_PSS_003
-
Excavation Permit
-
Confined Space Entry Permit
-
Valid Q form
-
Select date
-
Checked By
- Yes
- No
- N/A
3. Construction Plant and Equipment
-
Daily pre-start checklists completed for all plant
-
CSE equipment satisfactory
-
Plugs (not damaged)
-
Hoses (no leaks)
-
Select date
-
Checked By
- Yes
- No
- N/A
4. Service Location and Protection
-
"Dial Before You Dig" information <br>
-
All known existing services have been located and proved prior to work commencing
-
Minimum clearance maintained as per WSA 07-2007 or WSA 02-2002
-
Select date
-
Checked By
- Fiona Best
- Murray Doherty
- Quinnie Tranh
- Tony Dibben
- John Di Cosmo
5. Traffic Management
-
Set up as per site Traffic Management Plan
-
Works within specified road access time periods as stated in relevant MOA
-
Select date
-
Checked By
- Yes
- No
- N/A
6. Inspection of Materials
-
Pipe and fittings conform to specifications and are in new condition<br><br>As per standard drawing:<br><br>- SEW_PSS_003/PSS-1010-M Typical Isolation Valve Installation<br>- SEW_PSS_004 Flushing Point - Trafficable<br>- SEW_PSS_008/PSS-1012-M Flushing Point
-
Min PN16/SDR11, PE 100 and 316 SS Fittings
-
Valve/s clockwise closing
-
3mm gasket in good condition
-
Select date
-
Checked By
- Yes
- No
- N/A
7. Establish Environmental Controls (as per EMP)
-
Silt fencing set up where required
-
Silt traps employed where required
-
Parawebbing erected around protected trees/vegetation
-
Arborist onsite for excavation within a SRZ
-
Select date
-
Checked By
- Yes
- No
- N/A
8. Excavation
-
Sufficient traffic management and signs around excavation
-
Adequate fall from heights protection installed where required
-
Spoil stored correctly or removed from site
-
Correct trenching and shoring methods used for excavations greater than 1.5m
-
Select date
-
Checked By
- Yes
- No
- N/A
9. Isolation Valve Location
-
Ensure correct fittings and pit covers are used (Trafficable or non Trafficable)
-
Is this a bridge crossing? Valves required on either side of crossing
-
Flanges wrapped in blue plastic
-
Select date
-
Checked By
- Yes
- No
- N/A
10. Flushing Pit Location
-
Ensure correct fittings and pit covers are used (Trafficable or non Trafficable)
-
Intermediate flushing point is a minimum 1000mm or 12 x diameter from valves (whichever is greater)
-
Select date
-
Checked By
- Yes
- No
- N/A
11. Concrete Placement
-
Concrete placed in accordance with WSA-07-2007 Clause 14.6.5
-
Free fall is less than 1.6m
-
Concrete is immediately compacted after placing (ensure segregation off concrete ingredients does not occur)
-
Formwork remains in place until adequate concrete strength has been achieved
-
Select date
-
Checked By
- Yes
- No
- N/A
13. Bedding of Pipe for Open Cut
-
Bottom of trench is free from sharp obstructions
-
Min 100mm compacted sand on bed of trench
-
Min 150mm compacted sand surrounding pipe
-
Marker Tape installed on top of bedding material (min 150mm above pipe)
-
Select date
-
Checked By
- Yes
- No
- N/A
14. Compaction and Backfill
-
Backfill to MRWA Specification No. 04-03.1 or to Road Authority's requirements
-
The Road Authority's requirements shall take precedence if they exceed the requirements of the MRWA Specification.
MRWA Specification for roadways:
- up to 1.5m deep - 20mm Class 2 Plant Mixed Wet Mix Crushed Rock
- Over 1.5m - top 600mm to be 20mm Class 2 Plant Mixed Wet Mix Crushed Rock, 20mm Class 4 Crushed Rock for remainder.
- Excavations in Footpaths - 20mm Class 4
- Backfill placed in 200mm layers and compacted to required density 95% AS. -
Compaction Test Report/s received
-
Select date
-
Checked By
- Yes
- No
- N/A
15. Acceptance Testing
-
Pressure Testing for gravity system (vacuum or low air pressure testing)
-
Deflection testing (to be done 14 days after compaction has been completed)
-
CCTV received and satisfactory
-
Select date
-
Checked By
- Yes
- No
- N/A
16. Reinstatement
-
Construction Impact Zones and affected work areas restored to condition prior to commencement of works
-
All surplus material removed from site
-
Select date
-
Checked By
- Yes
- No
- N/A
NOTES AND COMMENTS
South East Water Representitive
-
Add signature