Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Project No:

  • Catchment:

  • Sub Catchment:

  • CIZ No.

1. Planning and Approvals

  • All Plans/Permits valid and onsite - ie. Power Company, Council or VicRoads MOA

  • Date

  • Checked By

2. Construction Documentation

  • SWMS relevant for specific site

  • Constructed as per standard drawing

  • Excavation Permit

  • Confined Space Entry Permit

  • Valid Q form

  • Date

  • Checked By

3. Construction Plant and Equipment

  • Daily pre-start checklists completed for all plant

  • CSE equipment satisfactory

  • Fall from heights equipment/gear

  • Plugs (no damage)

  • Hoses (no leaks)

  • Date

  • Checked By

4. Service Location and Protection

  • "Dial Before You Dig" information <br>

  • All known existing services have been located and proved prior to work commencing

  • Minimum clearance maintained as per WSA 07-2006 or WSA 02-2002

  • Date

  • Checked By

5. Traffic Management

  • Set up as per site Traffic Management Plan

  • Works within specified road access time periods as stated in MOA

  • Date

  • Checked By

6. Inspection of Materials

  • Pipe and fittings conform to specifications and are in new condition

  • As per standard drawings SEW_PSS_006 or SEW_PSS_007

  • Date

  • Checked By

7. Establish Environmental Controls (as per TMP)

  • Silt fencing set up where required

  • Silt traps employed where required

  • Parra webbing erected around protected trees/vegetation

  • Date

  • Checked By

8. Excavation

  • Sufficient traffic management and signs around excavation

  • Adequate fall from heights protection installed where required

  • Correct trenching and shoring method uses for excavations greater than 1.5m deep

  • Spoil stored correctly or removed from site

  • Date

  • Checked By

9. Deconstruct existing Manhole

  • Sewerage flow diversion in place if required

  • Correct Q form in place and active

  • Appropriate CSE gear used

  • SWMS provided and approved

  • Appropriate removal/disposal of existing structure and materials

  • Date

  • Checked By

10. Testing of Concrete

  • Is this a designated MH to be tested? (1 in 5 MH's to be tested per catchment/project)

  • Acceptable slump? (Ie. 80mm +- 15mm)

  • SEW approved product/supplier used

  • Concrete a minimum 25Mpa

  • Received a copy of delivery docket, 28 day strength test and completed concrete works ITP

  • Date

  • Checked By

11. Concrete Placement

  • If this is a discharge MH, has it been constructed in accordance with drawing PSS-1018-M (ie. 1200mm in diameter)

  • Concrete to be placed in accordance with WSA-02-2002 clause 14.5.5

  • Freefall to be less than 1.6m

  • Concrete to be immediately compacted after placing (ensure segmentation of concrete ingredients does not occur)

  • Formwork has not been stripped until adequate concrete strength has been achieved

  • Date

  • Checked By

12. Finished Manhole

  • Constructed to design specification

  • Pipe connector flush with MH internal wall

  • Pipe connector/stub sealed off for future connection

  • Step irons are in accordance with SEW -1307-V

  • No visible cracks/defects

  • As constructed levels recorded by surveyor

  • Date

  • Checked By

13. Unsealed Roadway

  • Is new MH located in an unsealed roadway.

  • Top of cover left 300mm below actual road surface

  • Photos taken prior to burial

  • Marker post installed as per standard drawing SEW_PSS_005

  • Date

  • Checked By

14. Compaction and Backfill

  • Backfill to MRWA Specification No. 04-03.1 or to Road Authority's requirements

  • The Road Authority's requirements shall take precedence if they exceed the requirements of the MRWA Specification.

    MRWA Specification for roadways:
    - up to 1.5m deep - 20mm Class 2 Plant Mixed Wet Mix Crushed Rock
    - Over 1.5m - top 600mm to be 20mm Class 2 Plant Mixed Wet Mix Crushed Rock, 20mm Class 4 Crushed Rock for remainder.
    - Excavations in Footpaths - 20mm Class 4
    - Backfill placed in 200mm layers and compacted to required density 95% AS.

  • Compaction Test Report/s received

  • Date

  • Checked By

15. Vacuum Testing of Manhole

  • Is this a designated MH to be tested? (1 in 5 MH's to be tested per catchment/project)

  • Did test pass? (Ie. vacuum pressure loss <= 5kPa after a minimum of 3 minutes)

  • If not, has MH been retested and passed?

  • Received copy of ITP

  • Date

  • Checked By

16. Epoxy Coating

  • Is this a discharge MH?

  • Has it been epoxy coated?

  • Received a copy of epoxy ITP

  • Date

  • Checked By

15. Reinstatement

  • Construction Impact Zones and affected work areas restored to condition prior to commencement of works

  • All surplus material removed from site

  • Date

  • Checked By

NOTES AND COMMENTS

South East Water Representitive

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.