INSPECTION OF MATERIALS

  • PIPE and FITTINGS conform to specification and in good condition?

  • Confirm Pressure Rating is PN 16 stated on the pipe?

  • Ensure Pipe installed is within the 12 Month period of Manufacturer's Date?

  • Confirm Pipe Colour?<br>PE is Black with Blue Stripe.<br>PVC is Blue ( Blue Brute).

  • Ensure Pipes and Fittings are stored as per the Manufacturer's recommendation?<br>Eg. END CAPS are installed on all Pipes at all times unless connected?

BUTT WELDING PE PIPE

  • Welding Machine Calibration Certificate on site?

  • Has Welder Operator have appropriate Tickets on site?

  • Are pipe ends cleaned, prior to welding?

  • After welding, has pipe cooling time been achieved and recorded?

ELECTRO FUSION WELDING OF PE PIPE

  • Ensure pipe is ROUND?

  • Ensure outside of Pipe is scraped and cleaned with alcohol wipes before commencement of welding?

  • Ensure " NO WATER " is present while welding is in progress?<br>

BEDDING OF PIPE FOR OPEN CUT METHOD OF RENEWAL

  • Ensure Bottom of Trench is free from SHARP OBSTRUCTIONS?

  • Ensure Minimum 100mm of COMPACTED SAND is on BED OF TRENCH?

  • Ensure Minimum 150mm of COMPACTED SAND is surrounding the PIPE?

  • MARKER TAPE installed on top of Bedding Material? (Minimum 150mm above Pipe)

INSTALLATION OF ISOLATION VALVES

  • VALVES INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?

  • Ensure Minimum Clearance of 600mm is between VALVE and HYDRANT?

INSTALLATION OF HYDRANTS

  • HYDRANTS INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?

SERVICE CONNECTIONS

  • PROPERTY CONNECTIONS INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?

  • SIZING REQUIREMENTS are as per the APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?

  • Minimum 500mm Clearance between each PROPERTY CONNECTION is Achieved?

  • PROPERTY CONNECTION FERRULES are installed at 90 Degrees to the new Water Main?

  • Are any PROPERTY CONNECTIONS installed with different offset from original position?<br>If " YES ", has TRACE WIRE been installed?

ENVIRONMENT

  • Approval Obtained to remove any Trees or Vegetation if required?<br>If " YES " is permit on site and available?

  • CRITICAL ROOT ZONE (50mm or Greater), have roots been cut at 90 Degress?

  • SEDIMENT CONTROL - Are SILT TRAPS installed and effective?

THRUST RESTRAINTS

  • Are THRUST RESTRAINTS installed as per the APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.