INSPECTION OF MATERIALS
-
PIPE and FITTINGS conform to specification and in good condition?
-
Confirm Pressure Rating is PN 16 stated on the pipe?
-
Ensure Pipe installed is within the 12 Month period of Manufacturer's Date?
-
Confirm Pipe Colour?<br>PE is Black with Blue Stripe.<br>PVC is Blue ( Blue Brute).
-
Ensure Pipes and Fittings are stored as per the Manufacturer's recommendation?<br>Eg. END CAPS are installed on all Pipes at all times unless connected?
BUTT WELDING PE PIPE
-
Welding Machine Calibration Certificate on site?
-
Has Welder Operator have appropriate Tickets on site?
-
Are pipe ends cleaned, prior to welding?
-
After welding, has pipe cooling time been achieved and recorded?
ELECTRO FUSION WELDING OF PE PIPE
-
Ensure pipe is ROUND?
-
Ensure outside of Pipe is scraped and cleaned with alcohol wipes before commencement of welding?
-
Ensure " NO WATER " is present while welding is in progress?<br>
BEDDING OF PIPE FOR OPEN CUT METHOD OF RENEWAL
-
Ensure Bottom of Trench is free from SHARP OBSTRUCTIONS?
-
Ensure Minimum 100mm of COMPACTED SAND is on BED OF TRENCH?
-
Ensure Minimum 150mm of COMPACTED SAND is surrounding the PIPE?
-
MARKER TAPE installed on top of Bedding Material? (Minimum 150mm above Pipe)
INSTALLATION OF ISOLATION VALVES
-
VALVES INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?
-
Ensure Minimum Clearance of 600mm is between VALVE and HYDRANT?
INSTALLATION OF HYDRANTS
-
HYDRANTS INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?
SERVICE CONNECTIONS
-
PROPERTY CONNECTIONS INSTALLED as per APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?
-
SIZING REQUIREMENTS are as per the APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?
-
Minimum 500mm Clearance between each PROPERTY CONNECTION is Achieved?
-
PROPERTY CONNECTION FERRULES are installed at 90 Degrees to the new Water Main?
-
Are any PROPERTY CONNECTIONS installed with different offset from original position?<br>If " YES ", has TRACE WIRE been installed?
ENVIRONMENT
-
Approval Obtained to remove any Trees or Vegetation if required?<br>If " YES " is permit on site and available?
-
CRITICAL ROOT ZONE (50mm or Greater), have roots been cut at 90 Degress?
-
SEDIMENT CONTROL - Are SILT TRAPS installed and effective?
THRUST RESTRAINTS
-
Are THRUST RESTRAINTS installed as per the APPROVED " ISSUED FOR CONSTRUCTION DRAWINGS "?
-
Add signature