Title Page

  • Conducted on

  • Prepared by

4.0 MANAGEMENT STANDARD

  • 4.1.1 What is the current status of outstanding NCR’s

  • 4.1.2 What are the current outstanding observations on the project?<br>

  • 4.1.3 Have all personnel on site been inducted?

  • 4.1.4 Are there appropriate resources and specialists identified and in place based on site?

  • 4.1.5 Are there any open NCR’s on the system for the project which need closing? (site only)

  • 4.1.6 Has a CPP (Construction Phase Plan) been established and reviewed?

  • 4.1.7 Has the CPP been briefed to all personnel on site? Inc. Magnox Managers.

  • 4.1.8 Are there JFN policies, HSE Law poster and other information freely available / displayed in a prominent position?

  • 4.1.9 Is there an EHS Committee in place?

  • 4.1.10 Have any accidents / incidents occurred? If so, have the reports been generated / investigated?

  • 4.1.11 Have any observations occurred? If so, have the reports been generated / investigated?

  • 4.1.12 Have weekly inspections been carried out? If so, have any observations / NCR’s been raised as a result?

  • 4.1.13 Have any Senior Management Engagement Tours been carried out? If so, have any observations / NCR’s been raised as a result?

  • 4.1.14 Have competency cards been reviewed for personnel on site? Including contractors (choose 3no. personnel)

  • 4.1.15 Is the ratio of subcontractor supervisors effective?

  • 4.1.16 Is there a Risk Assessment in place for the office / site / Building / Area?

  • 4.1.17 Does the Risk Assessment include manual handling, fire, legionella etc.?

  • 4.1.18 Have the hierarchy of controls in place within the Risk Assessment?

  • 4.1.19 Is Sub-contractor SSOW in place, including T Cards etc.?

  • 4.1.20 Have the SSOW been implemented on site? (choose 1no. contractor)

  • 4.1.21 Are there adequate welfare facilities in place?

  • 4.1.22 Is the Emergency Response Plan in place and up to date?

  • 4.1.23 Is the Traffic Management Plan in place and up to date?

  • 4.1.24 Is there adequate fire management in place (RA, means of escape, extinguishing equipment)?

  • 4.1.25 Is there adequate First Aid cover in place and equipment available?

  • 4.1.26 Is there an accident book available?

  • 4.1.27 Is there a behavioural safety champion in place?

  • 4.1.28 Is the Site Waste Management Plan in place and up to date?

  • 4.1.29 Are plan of the day and plan of the week meetings in place & being carried out? If so, who attends?

  • 4.1.30 For office staff, has DSE Assessments been carried out? If so, are there any issues?

  • 4.1.31 Has PAT Testing been carried out?

  • 4.1.32 Are office areas tidy, free of slips & trips?

  • 4.1.33 JFN - How are you recording defects and how are you closing them out?

  • 4.1.34 JFN - Are the Quality Plans signed and up to date? (Not passing hold points)

  • 4.1.35 JFN - Do you have a method in preparation for collating the LTR’s

  • 4.1.36 Trant - How are you recording defects and how are you closing them out?

  • 4.1.37 Trant - Are the Quality Plans signed and up to date? (Not passing hold points) Check certs for hold points (care / 3.1 certs for rebar & certs for a concrete batch, slump tests, pour check list)

  • 4.1.38 Trant - Do you have a method in preparation for collating the LTR’s for the ICF?

CONSTRUCTION SITE INSPECTION

  • 4.1.39 Are general storage areas clean, tidy and well demarcated?

  • 4.1.40 Are Traffic Management measures in place and suitable?

  • 4.1.41 Is there any Slip, Trip & Fall hazards?

  • 4.1.42 Are measures for cleaning up spills in place?

  • 4.1.43 Is there any hazardous waste present, how is it segregated?

  • 4.1.44 Is there COSHH present on site? Is it adequately stored, and are there COSHH Assessments available (with SDS)?

  • 4.1.45 How is dust controlled?

  • 4.1.46 Is there any power tools being used on site, if so have the operatives had HAVS training, are they recording their trigger times.

  • 4.1.47 Is there any face fit testing completed (if needed)?

  • 4.1.48 Is PPE issued, worn and adequate (in line with SSOW)?

  • 4.1.49 Excavations – is access / egress suitable?

  • 4.1.50 Excavations – is there general soundness & protection in place (shoring)

  • 4.1.51 Are excavated materials managed accordingly? Inc. contaminated land

  • 4.1.52 Plant & machinery – have all daily plant checks been carried out?

  • 4.1.53 Is lifting equipment suitably checked and maintained?<br>

  • 4.1.54 Have any manual handling assessments been carried out?

  • 4.1.55 If applicable, for any portable tools, have a HAVS induction been carried out?

  • 4.1.56 What plans are in place for the management of surface and ground water

  • 4.1.57 Is plant and machinery suitable for the task in place and are they in good order?

  • 4.1.58 Is there a trained banksman in place?

  • 4.1.59 Is there adequate signage in place?

  • 4.1.60 Is there suitable lighting in place for work areas?

  • 4.1.61 Please state any improvements to be made and any positive observations during the time of the audit?<br>

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.