Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Handover Criteria
-
Gross internal area measure check
-
Wind, weather tight and secure, all external fabric / cladding complete
-
Party walls complete
-
Internal accommodation - walls complete (Sales to warehouse dividing wall to be 1hr rated and acoustically sealed)
-
Plant & refuse enclosure complete (Slab, drainage, fencing)
-
All main services brought into building (Power, water, BT, drainage - ducts into building for carpark lighting, BT and totem)
-
Slab / Screed complete and adequately cured. Floor slab finish 3mm over 3m, flush level access across thresholds to all entrance doors?)
-
All temporary works complete as required: hoardings to shopfront, fencing to site and compounds, temporary fire alarms etc. As required by landlord, fire officer, building<br>control.
-
All external works complete.<br>(Rainwater goods metal RAL7043, external gulley and channel gratings to prevent hazard to customers, trollies?) Manhole covers / inspection chambers to avoid entrance locations and access routes.<br>Landscaping and boundary treatments? Sensitive boundaries - screening - LPA? Car park - (qty spaces, surface drainage, circulation, access?) External lightings?
-
Freezer and matwell recess formed. (Freezer +9m2 requires 125mm recess, matwell recess to be 17mm in depth)
-
Shopfront, auto doors and roller shutters complete (composite panel in place for external ATM)
-
External doors (Soham clear opening of 1050mm)
-
Confirmation that no 3rd party services or ducts are routed through the proposed demised area.
-
Totem base, cage and ducts complete?
-
Section 106 / 278 works complete?
Schedule of defects and outstanding works to be included within the Shell practical completion certificate.
-
Defect Details
Item
-
Add media
Technical Information
-
Electronic copy of planning permissions and Documentation confirming all planning conditions are discharged to the satisfaction of the local authority.
-
Pre-construction information pack,<br>Construction phase health and safety plan<br>including<br>F10 notification.<br>Form of contract.<br>Project directory.<br>Programme of works.<br>COSHH and technical data sheets.
-
Building control completion certificate.
-
Fire officer approval, comments.
-
Written confirmation from the highways authority that any highway works have been satisfactorily completed. Section 278 agreements to be included within file.
-
Party wall completion certificate.
-
Independent roof inspection report with designers comments where applicable.
-
Structural survey and calculations.
-
CCTV survey demonstrating satisfactory drainage both new and where existing is reused with designers comments / acknowledgements. (Access points for rodding to be detailed).
-
Fire stopping installation and accreditation certificate.
-
Steelwork finishes - Certificate for intumescent paint where used.
-
Floor slab compliance survey, engineers confirmation of minimum imposed uniformly distributed live loading of 7.5kn/ m2.
-
Floor level survey if applicable.
-
Geotechnical survey.
-
Approved external lighting scheme.
-
Approved landscaping scheme and layout.
-
Energy performance certificate (EPC)
-
SBEM carbon emissions calculation and BRUKL report together with air leakage test results to show compliance with Part L2A. Required for new builds or where change of use.
-
BREEAM rating required as part of developers permissions?
-
Asbestos R&D survey report.
-
Documentation to confirm the removal of asbestos including the results of an air particle test.
-
Delivery strategy tracking drawing.
-
Acoustic survey and report.
-
Ecology Survey
-
Utilities - moving out, change of tenancy forms (meter readings to be taken)
Electronic drawings (in PDF & DWG)
-
Site plan showing access and egress from site, refuse and delivery points and all estate signage locations.
-
Location plan.
-
Demise Plan
-
GA Plan
-
Existing (where applicable) building plans and elevations.
-
Proposed building plans and elevations.
-
Identification of service risers and openings.
-
Internal service routes including drainage.
-
Roof & Section plans
Warranties
-
Collateral Warranties<br>Architects, Engineers, Principal Designers
-