Information
-
DA and CC Number
-
Applicant / Client / Owner
-
Conducted on
-
Prepared by
-
Location
Consent Details
-
DA/CDC/CC No.
-
Address
Previous inspections
-
- Footings
- Slab Steel
- Stormwater
- Bearers and Joists
- Wet Area
- Frame
- Final
Onsite Inspection
-
Are there any outstanding items from previous inspections?
-
Are there any environmental controls stated in the development consent installed on site?
-
The following controls have been checked for compliance
- Builders sign
- Sediment and Erosion controls
- Builders Toilet
- Protection of public space by fencing or hoarding
- protection and support of adjoining buildings
- Waterboard stamped plans
-
Is the building under construction consistent with the consent and specifications including any modifications?
-
Have relevant conditions of the consent required to be incorporated in the construction of the building, been implemented
-
Have relevant BASIX commitments been implemented?
Component: Frame
-
Do the following components comply with the BCA, Engineers design and/or manufacturer's specifications?
-
Subfloors
-
Subfloor braces?
-
Timber preservative treatment/s (termite control) ?
-
Ant capping ?
-
Point load/bearing joists ?
-
Ventilation ?
-
Mechanical connections ?
-
Bolted connections ?
-
Timber sizes/spans ?
-
Solid blocking ?
-
Bearers and joists ?
-
Floors
-
Joists ?
-
Substrate fixing for membranes ?
-
Timber preservative treatment (termite control) ?
-
Timber sizes/spans ?
-
Point load/bearing joists ?
-
Timber beams ?
-
Steel beams ?
-
Walls
-
External bottom plate fastening ?
-
Internal bottom plate fastening ?
-
Bracing ?
-
Brace height ?
-
Brace fixing ?
-
Crippling of stud ?
-
Timber sizes/span ?
-
Framing notches/holes ?
-
Nail plates ?
-
Lintel size/ fixing/ support ?
-
Damp proof course/ flashings ?
-
Timber preservative treatment (termite control) ?
-
Roof
-
Pitch/type ?
-
Purlin fixing ?
-
Rafter straps/ concealed purlin cleats ?
-
Ceiling batten fixing ?
-
Truss spacing/tie downs ?
-
Secondary bracing, ceiling/roof ?
-
Steel Frame
-
Does the steel frame comply with the BCA / Engineers Design / Specifications ?
Component: Structural Steel
-
Do the following components comply with the BCA, Engineers design and/or manufacturer's specifications?
-
Has the structural steelwork been installed as per structural engineer's design?
-
Has the structural steelwork been connected and fastened as per structural engineer's design?
-
Have relevant conditions of the consent required to be incorporated in the construction of the building been implemented?
Component: Masonry
-
Do the following components comply with the BCA, Engineers design and/or manufacturer's specifications?
-
Suitable for location ?
-
Cavity ?
-
Perpends ?
-
Width ?
-
Cleanliness of cavity ?
-
Weepholes ?
-
Articulation joints ?
-
Fixing straps and tie down systems ?
-
Lintels ?
-
Damp proof membrane ?
-
Wall tiles, size/spacing ?
-
Mortar mix ?
-
Isolated piers ?
-
Flashing correctly installed (windows, doors, roofs, parapets, chimney) ?
SUMMARY
-
Result
-
Comments
-
Photos
-
Accredited Certifier
-
Conducted on
-
Signature
-
PO Box 155, Shellharbour City Centre 2529 -Phone 02 4221 6111 -Fax 02 4221 6016 -Email records@shellharbour.nsw.gov.au. -Web www.shellharbour.nsw.gov.au -DX 26402 Shellharbour City Centre