Information

COFELY SHIFT ENGINEERING LOG

Handover Sheet

Current Shift Information

  • Date

  • Shift

  • Shift Engineer

Plant Failures

  • Add New Plant Failure

  • Plant Failure No.
  • Description

  • Repaired {If no add detail of works required}

Daily Work Log - Start and Finish Times to be Recorded for all Entries

  • Add New PPM or Reactive Job

  • Job
  • SELECT JOB TYPE

  • PPM NUMBER AND DESCRIPTION

  • PPM START TIME

  • PPM FINISH TIME

  • DO PARTS NEED TO BE ORDERED? IF SO ENTER DETAILS AND PHOTOGRAPH IF NEEDED

  • REACTIVE JOB DESCRIPTION

  • WAS THE CALL ISSUED FROM SECURITY?

  • TIME CALL RECEIVED

Checks

  • Plant Walk-round completed {Days}

  • BMS checks carried out

  • CGH CHILLER SCREENSHOT

  • 50 FINSBURY CHILLER SCREENSHOT

  • 38 FINSBURY CHILLER SCREENSHOT

  • CGH BOILER SCREENSHOT

  • CGH FRONT OF HOUSE BOILER SCREENSHOT

  • 50 FINSBURY BOILER SCREENSHOT

  • 38 FINSBURY BOILER SCREEN SHOT

  • LONDON FDSK QUEUE CHECKED.

  • HAVE ALL CRITICAL FDSK'S BEEN UPDATED?

  • 30 MIN LIGHTING WALK-ROUND

  • WE'RE ANY REMEDIAL WORKS CARRIED OUT?

  • FDSK NUMBER

  • TIME STARTED

  • TIME COMPLETED

Handover Information

  • Shift Handover carried out

  • Information to be Passed to Next Shift or Other Requests from Bloomberg/Security

Signatures

  • Engineer Finishing Shift

  • Engineer Starting Shift, Keys and Blackberry Recieved

LG training rooms

Lower ground floor training rooms temperature checks

  • Average temp room 1

  • Average temp room 2

  • Average temp room 3

  • Average temp room 4

CHILLED WATER TEMPS

  • CITY GATE HOUSE CHILLED WATER FLOW TEMP

  • Has chiller 5 started (if the BMS has not automatically started chiller 5 click the override button)<br>

  • If the BMS has not started chiller 5, go to the chiller on the roof of city gate house and turn on locally. If this fails escalate the issue

  • 50 FINSBURY CHILLED WATER FLOW TEMP

  • Check chillers, reset if needed.<br><br>HAS THIS RECTIFIED THE ISSUE?

  • ESCALATE THE ISSUE

  • 38 FINSBURY CHILLED WATER FLOW TEMP

BOILER TEMPS

  • CITY GATE HOUSE LANDLORDS BOILER IS THE TEMP ABOVE 50C? <br>HAS THE COMPENSATED HEATING REACHED SET POINT?

  • HAS THERE BEEN A POWER LOSS? <br>


  • RESET THE MAIN GAS VALVE AND THE RESET THE TREND PANEL IN THE BOILER ROOM

    (The reset is in the favourites folder in the touch screen panel)

    ALSO ENSURE THAT THE GAS BOOSTER PUMP PRESSURE SWITCHES HAVE BEEN RESET.

    IF THIS FAILS CHECK THAT ALL OF THE BREAKERS AND OVERLOADS IN THE BOILER PANEL ARE RESET

  • IS THE TEMP RISING IN BOTH THE PRIMARY AND SECONDARY CIRCUITS.

  • Escalate the issue, and ensure that DTZ (DAVE ROBERTSON, OR LEE DUDDY) have also been informed

  • CITY GATE HOUSE BOILER FLOW TEMP<br>IS THE TEMP ABOVE 50C?

  • IS THE BMS HOLDING THE HEATING OFF ON OUTSIDE AIR TEMP?

  • Check boilers, pressurisation unit, and pumps

  • 50 FINSBURY BOILER FLOW TEMP

  • IS THE BMS HOLDING THE HEATING OFF ON OUTSIDE AIR TEMP?

  • Check boilers, pressurisation unit, and pumps

  • 38 FINSBURY BOILER FLOW TEMP

  • IS THE BMS HOLDING THE HEATING OFF ON OUTSIDE AIR TEMP?

  • Check boilers, pressurisation unit, and pumps

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.