Information
-
Company Name: Shaw Installations Limited
-
Company Contact: Simon Shaw
-
Client: Insert Name
-
Client Site Location: Insert Location
-
Title: Site Inspection and Audit Report
-
Inspection Conducted By: Insert Name
-
Observed Activities: Mechanical & Electrical Engineering
-
Inspection Report Number:
-
Weather Conditions:
-
Inspection Conducted On:
Disclaimer and Confidentiality
-
Disclaimer:
The auditor believes the information contained within this inspection/audit report to be correct at the time of production. The auditor does not accept responsibility for any consequences arising from the use of the information herein. The report is based on matters which were observed or came to the attention of the auditor during the day of the inspection/audit and should not be relied upon as an exhaustive record of all possible risks or hazards that may exist or potential improvements that can be made. Information on the latest legislation and guidance can be found on the Health and Safety Executive website www.hse.gov.uk. -
Confidentiality Statement:
In order to maintain the integrity and credibility of the inspection/audit processes and to protect the parties involved, it is understood that the auditor will not divulge to unauthorised persons any information obtained during this inspection/audit unless legally obligated to do so.
Site Management and Operatives
-
Name of Principal Contractor (PC):
-
Name of PC Site Manager:
-
Name of SI Site Manager:
-
Name of SI Site Supervisor:
-
Name(s) of SI Site Operatives:
-
Name(s) of SI Subcontractors:
-
Name(s) of First Aiders:
-
Name(s) of Fire Marshals:
H&S Documentation
-
Has H&S Signage been installed at the Main Site Entrance?
-
Has the Principal Contractor (or Contractor) established a Construction Phase Health & Safety Plan?
-
Is the project notifiable to the HSE as per CDM 2015 Regulations?
-
Note: A construction project is notifiable if the construction work is expected to: last longer than 30 working days and have more than 20 workers working at the same time at any point on the project or exceed 500 person days
-
Is there a Site Plan showing Fire, First Aid and Emergency Arrangements?
-
Have all SI Operatives been provided with a site induction?
-
Have all SI Subcontractors been provided with a site induction?
-
Are the Welfare Facilities adequate and suitable for the project requirements?
-
Are the SI Operative RAMS suitable and sufficient for the observed tasks?
-
Are the SI Subcontractor RAMS suitable and sufficient for the observed tasks?
-
Have all SI Operatives signed the RAMS documents?
-
Have all SI Subcontractors signed the RAMS documents?
-
Has this project included Lifting Operations? (As defined by LOLER 1998)
-
Is there a documented Lift Plan? (As required by LOLER 1998)
-
Is there a documented Waste Management Plan?
-
Has the Principal Contractor implemented a Permit to Work system?
Plant & Equipment
-
Do the current SI work activities require the use of MEWPs?
-
Do the current SI work activities require the use of Forklift Trucks?
-
Do the current SI work activities require the use of a Telehandler?
-
Do the current SI work activities require the use of a Crane? (Mobile or Static)
-
Do the current SI work activities require the use of a Construction Hoist?
-
If Yes to any of the above, are the LOLER Thorough Examination Certificates available and in date?
-
Is there an asset list of Hand Held Power Tools?
-
Do the current SI work activities require the use of Step Ladders or Hop-Ups?
Collective Protection
-
Edge Protection in place, suitable & inspected?
-
Access / Egress in place, suitable & inspected?
-
Pedestrian access routes in place & suitable?
-
Plant/Traffic Segregation, are routes in place & suitable?
-
Ground Conditions well maintained for pedestrian and plant access?
-
Further Collective Protection Comments?
Personal Protective Equipment (PPE)
-
Have the minimum requirements for PPE been defined by Site Management?
-
Are All SI Operatives wearing Mandatory i.e. Hi-Vis vests, Safety boots & Hard Hats?
-
Are All SI Subcontractors wearing Mandatory i.e. Hi-Vis vests, Safety boots & Hard Hats?
-
Is Task Specific PPE available as required?
-
Is there any further or additional PPE required?
H&S Records
-
Review of Operative Site Access Records (sign-in/sign-out)
-
Review of Accident Book
-
Review of First Aid Provisions
-
Review of PAT Records
-
Review of Safe Start Briefings
-
Review of Toolbox Talks
-
Review of Plant Inspections (FLT, MEWP etc)
-
Review of Plant Certificates
-
Review of Step Ladder or Hop-Up Inspections
-
Review of Operative ECS or CSCS Cards
-
Review of Plant Operator Certificates and or Cards
-
Review of COSHH Safety Data Sheets
-
Review of HAVs Risk Assessment
-
Review of PPE Issue/Inspection Register
-
Review of PTW Records
Material & Waste Management
-
Are SI operatives maintaining tidy work areas?
-
Are other trades maintaining tidy work areas?
-
Are SI Materials stored securely & safely?
-
Is the Waste Container or Skip provision suitable?
-
Are refuelling / fuel storage arrangements suitable?
-
Have Spill kits been provided?
Observations & Inspection Summary
-
Other Items or Concerns Observed During the Audit
Summary
-
Insert Feedback from Visual Inspection (Detail Any Faults Found)
-
Inspection Completed By:
-
Inspection Completion Date: