Information

  • Report Title

  • Client / Site

  • Conducted on

  • Project Team Members:

Pre-Installation Admin

  • Actual Project Address:

  • Project Number:

  • Inspection W/O #:

  • Date of Inspection:

  • Physicist Name:

  • IT responsible Name:

  • Any other considerations or comments on the above?

Data Center

  • Is there a Data Center on the site for project implementation?

  • Where will be installed the Server and components?

  • Are the painting, inside finishing, furniture already installed and finished?

  • Are the air conditioning functional?

  • New Moisaq Server to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • Is there space available to install the Mosaiq Server Monitor 19"?

  • New Dicom Namer to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • Is there space available to install the Dicom Namer Monitor 19"?

  • New Backup unit of Mosaiq to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New ESI to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New direct access to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New direct storage to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New No break to be installed?

  • Is there space available about 1m² to install?

  • Is there 2 units of power plug about 110V/ 220V 3KVA Steck standard?

  • What is voltage?

  • Any comments:

Planning Area

  • Is the painting, internal finishing, furniture already installed and functional?

  • Are the air conditioning functional?

  • If the site does not include a Data Center, then the Mosaiq Server and its components should be installed from the Planning Area.

  • New Moisaq Server to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • Is there space available to install the Mosaiq Server Monitor 19"?

  • New Dicom Namer to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • Is there space available to install the Dicom Namer Monitor 19"?

  • New Backup unit of Mosaiq to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New ESI to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New Moisaq Server to be implemented?

  • Witch type of server, rack or tower?

  • Is there space available about 3 "U"?

  • Is there space available on the floor about 1m²?

  • New No break to be installed?

  • Is there space available about 1m² to install?

  • Is there 2 units of power plug about 110V/ 220V 3KVA Steck standard?

  • What is voltage?

  • Is a Monaco to be implemented?

  • Is 80cm of free space available at planning desk?

  • 110/220V power plug available?

  • Data connection RJ45 CAT 6 available, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • Is a Monaco Sim to be implemented?

  • To be installed at?

  • Is 80cm of free space available at planning desk?

  • 110/220V power plug available?

  • Data Connection RJ45 CAT6 available, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • Where?

  • Is 80cm of free space available at the desk?

  • 110/220V power plug available?

  • Data connection RJ45 CAT6 available, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • New Mosaiq workstations to be implemented?

  • How many Mosaiq workstations?

  • All Mosaiq workstations will be installed at planning area?

  • Is 80cm of free space available at planning desk for each Mosaiq workstation?

  • 110/220V power plugs available for each Mosaiq workstation?

  • Data connection RJ45 CAT 6 available for each Mosaiq worskstation, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • How many Mosaiq workstation will be installed out of planning area?

  • What are the locations?

  • Is 80cm of free space available at desk for each Mosaiq workstation?

  • 110/220V power plugs available for each Mosaiq workstation?

  • Data connection RJ45 CAT 6 available for each Mosaiq worskstation, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • How many Mosaiq workstation will be installed at planning area?

  • Is 80cm of free space available at desk for each Mosaiq workstation?

  • 110/220V power plugs available for each Mosaiq workstation?

  • Data connection RJ45 CAT 6 available for each Mosaiq worskstation, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • New ABAS library to be implemented?

  • Is 80cm of free space available at planning desk?

  • 110/220V power plug available?

  • Data connection RJ45 CAT 6 available, connected to the client network and functional?

  • Opening about 3" for cable pass?

  • Any comments:

Control Area

  • Attention!
    Do not forget the needed space on the control desk for the Linac stuffs: TCC, IView, XVI, Apex, IGuide, CCTV and Printers.

  • Select:

  • Is the painting, internal finishing, furniture already installed and functional?

  • Are the air conditioning functional?

  • New Mosaiq Sequencer/ Synergistiq to be implemented?

  • Is 80cm of free space available at desk for each Mosaiq workstation?

  • 110/220V power plugs available for each Mosaiq workstation?

  • Data connection RJ45 CAT 6 available for each Mosaiq worskstation, connected to the client network and functional?

  • New Mosaiq workstation to be implemented at control area?

  • How many Mosaiq workstation

  • Is 80cm of free space available at desk for each Mosaiq workstation?

  • 110/220V power plugs available for each Mosaiq workstation?

  • Data connection RJ45 CAT 6 available, connected to the client network and functional?

  • Any comments:

Networking

  • Are the client networking available, tested and functional?

  • Are the data cabling RJ45 CAT 6 standard?

  • Are the switches 1 Gigabite quality?

  • Are the switches exclusives for Elekta implementation?

  • Does the customer intends to connect the RM to the Elekta system?

  • NAME:

  • PORT:

  • IP:

  • TITLE:

  • Dos the customer intends to connect the Tomography to the Elekta system?

  • NAME:

  • PORT:

  • IP:

  • TITLE:

  • Is an internet available to download software and to help onsite implementation?

  • Any other considerations or comments on the above?

Inspection Notes

  • Inspection type:

  • Is the site ready to start the implementation of HW & SW?

  • Select date

  • Responsible to complete the report:

  • Add signature

  • physicist name:

  • Add signature

  • IT responsible name:

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.